03 11 13 CREW DAILY UNIT TOTAL INCL. O&P BARE COSTS Concrete Forming OUTPUT MAT. INST. TОTAL 13.25 6500 FORMS IN PLACE, COLUMNS 24"X 24" plywood columns, 1 use C-1 190 S.F.C.A 2.64 6.10 8.74 12.35 Suare Foot Contact Area General work description Crew C-1 Crew No. Bare Costs Incl. Subs 0&P Daily 1423.20 376.40 $ 1799.60 Crew C-1 Hr. Daily 914.40 Hr. 59.30 3 Carpenters 1 Laborer 32 L.H. Daily Total 38.10 242.00 $1156.40 30.25 47.05 Line iten determination: (These figures are printed above) BARE COSTS are developed as follows: MAT. is 2.64/SFCA Major UCI subdivision = 03.11 Major classification within subdivision =13.25 INST. Crew C-1 Daily Bare Cost = 1156.40 = $6.10/SFCA (rounded) Daily Output 190 Line item number = 6500 TOTAL = MAT. + INST. = $2.64+ $6.10= $8.74per S.F.C.A. Complete line number: 03 11 13.25 6500 (Only the total of these figures is printed above) TOTAL COSTS INCL. O&P are developed as follows- MAT. is BARE MAT. + 10% = 2.64 + 0.26 = $2.90/SFCA INST. Crew C-1 Daily Bare Cost - $ 1799.60:9.45/SFCA (rounded) Daily Output 190 TOTAL = MAT. + INST. = $2.90+ $9.45= $12.35/SFCA
03 11 13 CREW DAILY UNIT TOTAL INCL. O&P BARE COSTS Concrete Forming OUTPUT MAT. INST. TОTAL 13.25 6500 FORMS IN PLACE, COLUMNS 24"X 24" plywood columns, 1 use C-1 190 S.F.C.A 2.64 6.10 8.74 12.35 Suare Foot Contact Area General work description Crew C-1 Crew No. Bare Costs Incl. Subs 0&P Daily 1423.20 376.40 $ 1799.60 Crew C-1 Hr. Daily 914.40 Hr. 59.30 3 Carpenters 1 Laborer 32 L.H. Daily Total 38.10 242.00 $1156.40 30.25 47.05 Line iten determination: (These figures are printed above) BARE COSTS are developed as follows: MAT. is 2.64/SFCA Major UCI subdivision = 03.11 Major classification within subdivision =13.25 INST. Crew C-1 Daily Bare Cost = 1156.40 = $6.10/SFCA (rounded) Daily Output 190 Line item number = 6500 TOTAL = MAT. + INST. = $2.64+ $6.10= $8.74per S.F.C.A. Complete line number: 03 11 13.25 6500 (Only the total of these figures is printed above) TOTAL COSTS INCL. O&P are developed as follows- MAT. is BARE MAT. + 10% = 2.64 + 0.26 = $2.90/SFCA INST. Crew C-1 Daily Bare Cost - $ 1799.60:9.45/SFCA (rounded) Daily Output 190 TOTAL = MAT. + INST. = $2.90+ $9.45= $12.35/SFCA
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
Related questions
Question
Find the labor cost, including overhead and profit for the
formwork for 48 columns of 24ʺ × 24ʺ × 9ʹ. Use the data
shown in Figure 17.7.

Transcribed Image Text:03 11 13
CREW
DAILY
UNIT
TOTAL
INCL. O&P
BARE COSTS
Concrete Forming
OUTPUT
MAT.
INST.
TОTAL
13.25
6500
FORMS IN PLACE, COLUMNS
24"X 24" plywood columns, 1 use
C-1
190
S.F.C.A
2.64
6.10
8.74
12.35
Suare Foot
Contact Area
General work description
Crew C-1
Crew No.
Bare Costs
Incl. Subs 0&P
Daily
1423.20
376.40
$ 1799.60
Crew C-1
Hr.
Daily
914.40
Hr.
59.30
3 Carpenters
1 Laborer
32 L.H. Daily Total
38.10
242.00
$1156.40
30.25
47.05
Line iten determination:
(These figures are printed above)
BARE COSTS are developed as follows:
MAT. is 2.64/SFCA
Major UCI subdivision = 03.11
Major classification within subdivision =13.25
INST. Crew C-1 Daily Bare Cost = 1156.40 = $6.10/SFCA
(rounded)
Daily Output
190
Line item number = 6500
TOTAL = MAT. + INST. = $2.64+ $6.10= $8.74per S.F.C.A.
Complete line number: 03 11 13.25 6500
(Only the total of these figures is printed above)
TOTAL COSTS INCL. O&P are developed as follows-
MAT. is BARE MAT. + 10% = 2.64 + 0.26 = $2.90/SFCA
INST. Crew C-1 Daily Bare Cost - $ 1799.60:9.45/SFCA
(rounded)
Daily Output
190
TOTAL = MAT. + INST. = $2.90+ $9.45= $12.35/SFCA
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 3 steps

Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.Recommended textbooks for you


Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON

Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning


Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON

Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning

Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education


Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning