MGT2_KKM1: Monitoring and Controlling Monitoring and Controlling Template Project Title Project Manager Customer Name Cloud Storage Migration Allie Gillaspy Pruhart Financial A. Risk Assessment Risk Description Likelihood (L, M, H) Impact (L, M, H) Responsible Person Prevention/Mitigation Strategy Concern over the possibility of needing to reroute the electricity cables in the older part of the building. M M Eva Miller Shielded cables are currently working at full capacity, but need to be inspected by the facilities team in September. Introducing two-factor authentication for end-user machines may lead to a setback in security management. H H Omar Patel Ensure two-factor authentication on all the servers and that all users are up and running. Duplicated Files H M Sara Phan All new hires are trained on what not to do with duplicate files. QA automation engineers need to be added as authorized users. H H Ren Sousa In order to complete the migration of data for testing, the QA automation engineers need to be added as authorized users as soon as possible. Monitoring the system during days that the company is closed for holidays. L H Ahmed Williams Decide if a team member is required to work during company holidays to monitor the system. Key: L=Low, M=Medium, H=High B. Gantt Chart The Gantt Chart is attached as a separate document titled Pruhart Financial.xml.pod . C1. Earned Value Analysis Team EV AC PV CV CPI SV SPI PAGE 1
MGT2_KKM1: Monitoring and Controlling Monitoring and Controlling Template Premigration $12,223.20 $12,525.00 $19,636.36 $-301.80 0.98 $-7,413.16 0.622 Storage $7,290.36 $7,425.00 $10,800.00 $-134.64 0.98 $-3,509.64 0.675 Off-Site Cloud System $3,166.80 $2,925.00 $3250.00 $241.80 1.08 $-83.20 0.974 Testing $3,762.42 $3,900.00 $3,532.26 $-137.58 0.96 $230.16 1.065 Migration 0 0 0 0 0 Total $26,442.78 $26,775.00 $37,218.62 $-332.22 1.00 $-10,775.84 0.834 C2. Earned Value Projections Team EAC ETC Est. Dur. Est. Completion Date Premigration $24,592.58 $12,067.58 22 September 5, 2023 Storage $12,832.70 $5,407.70 21 September 4, 2023 Off-Site Cloud System $33,097.17 $33,097.17 60 November 15, 2023 Testing $41,501.63 $41,501.63 62 November 17, 2023 Migration $14,400.00 $14,400.00 24 December 21, 2023 C3. Discussion of Earned Value Analysis and Projections Due to the project containing five separate teams, each team’s numbers were run individually, and then totals were provided to view the project as a whole. Currently, the PAGE 2
MGT2_KKM1: Monitoring and Controlling Monitoring and Controlling Template Premigration and Storage teams are behind schedule, and the Off-site Cloud System team is experiencing a delay. The Testing team is ahead of schedule and the Migration team is awaiting the completion of the Off-site team’s completion and one of the Testing team’s tasks to be completed to begin work. Specific team updates are provided below. Premigration - Eva Miller’s team has exceeded their allotted budget, as evidenced by their CPI of 0.98. The team has used a total of $12,525 from their allotted budget and is projected to need an additional $12,067.58 before the completion of the project. The team is projected to complete their tasks on September 5, 2023, but in order to successfully do so they will need an additional $24,592.58. Storage - Omar Patel’s team, is currently also exceeding their allotted budget. The team has used a total of $7,425 and is projected to incur an additional cost of $5,407.70 before the completion of the project. The team is projected to complete their tasks on September 4 and will need an additional $12,832.70. Off-site Cloud System - Sara Phan’s team has been successful in staying within their budget. The team has spent $2,925 so far and is projected to spend an additional $33,097.17. The team is on track to complete all tasks on November 15, 2023 and will require an additional $36,022.17. Testing - Ren Sousa’s team is performing just slightly over budget. They have spent #3,900.00 and will spend another $41,501.63 by the completion of the project. The team is currently working three days ahead of schedule and is projected to complete all tasks by November 17. Migration - Ahmed Williams’ team has not started their tasks yet, due to tasks assigned to other teams needing to be completed first. With the delay in their start time, the team’s ETC and EAC are still $14,400.00. The team is projected to complete all of their assigned project tasks by December 19. D1. Burndown Chart PAGE 3
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
  • Access to all documents
  • Unlimited textbook solutions
  • 24/7 expert homework help
MGT2_KKM1: Monitoring and Controlling Monitoring and Controlling Template D2. Discussion of Burndown Chart According to the burndown chart, the project remains encumbered with numerous outstanding tasks, surpassing those already completed. Notably, on day 18, our progress exceeded initial projections, evidenced by the completed tasks falling below the expected trajectory outlined by the orange line. E. Mitigation Plan The project is currently ahead of schedule and under budget, as seen in the Earned Value Analysis and the project Burndown Chart. The project team leaders should use mitigating strategies in order to ensure everyone stocks to the project's projected completion dates. The premigration team PAGE 4