MGT2_KKM1: Monitoring and Controlling
Monitoring and Controlling Template
Project Title
Project Manager
Customer Name
Cloud Storage Migration
Allie Gillaspy
Pruhart Financial
A. Risk Assessment
Risk
Description
Likelihood
(L, M, H)
Impact
(L, M, H)
Responsible
Person
Prevention/Mitigation
Strategy
Concern over the
possibility of needing
to reroute the
electricity cables in the
older part of the
building.
M
M
Eva Miller
Shielded cables are
currently working at
full capacity, but need
to be inspected by the
facilities team in
September.
Introducing two-factor
authentication for
end-user machines may
lead to a setback in
security management.
H
H
Omar Patel
Ensure two-factor
authentication on all
the servers and that all
users are up and
running.
Duplicated Files
H
M
Sara Phan
All new hires are
trained on what not to
do with duplicate files.
QA automation
engineers need to be
added as authorized
users.
H
H
Ren Sousa
In order to complete the
migration of data for
testing, the QA
automation engineers
need to be added as
authorized users as
soon as possible.
Monitoring the system
during days that the
company is closed for
holidays.
L
H
Ahmed
Williams
Decide if a team
member is required to
work during company
holidays to monitor the
system.
Key: L=Low, M=Medium, H=High
B. Gantt Chart
The Gantt Chart is attached as a separate document titled
Pruhart Financial.xml.pod
.
C1. Earned Value Analysis
Team
EV
AC
PV
CV
CPI
SV
SPI
PAGE 1
MGT2_KKM1: Monitoring and Controlling
Monitoring and Controlling Template
Premigration
$12,223.20
$12,525.00
$19,636.36
$-301.80
0.98
$-7,413.16
0.622
Storage
$7,290.36
$7,425.00
$10,800.00
$-134.64
0.98
$-3,509.64
0.675
Off-Site
Cloud System
$3,166.80
$2,925.00
$3250.00
$241.80
1.08
$-83.20
0.974
Testing
$3,762.42
$3,900.00
$3,532.26
$-137.58
0.96
$230.16
1.065
Migration
0
0
0
0
0
Total
$26,442.78
$26,775.00
$37,218.62
$-332.22
1.00
$-10,775.84
0.834
C2. Earned Value Projections
Team
EAC
ETC
Est. Dur.
Est. Completion Date
Premigration
$24,592.58
$12,067.58
22
September 5, 2023
Storage
$12,832.70
$5,407.70
21
September 4, 2023
Off-Site Cloud
System
$33,097.17
$33,097.17
60
November 15, 2023
Testing
$41,501.63
$41,501.63
62
November 17, 2023
Migration
$14,400.00
$14,400.00
24
December 21, 2023
C3. Discussion of Earned Value Analysis and Projections
Due to the project containing five separate teams, each team’s numbers were run
individually, and then totals were provided to view the project as a whole. Currently, the
PAGE 2
MGT2_KKM1: Monitoring and Controlling
Monitoring and Controlling Template
Premigration and Storage teams are behind schedule, and the Off-site Cloud System team is
experiencing a delay. The Testing team is ahead of schedule and the Migration team is awaiting
the completion of the Off-site team’s completion and one of the Testing team’s tasks to be
completed to begin work. Specific team updates are provided below.
Premigration
- Eva Miller’s team has exceeded their allotted budget, as evidenced by their CPI
of 0.98. The team has used a total of $12,525 from their allotted budget and is projected to need
an additional $12,067.58 before the completion of the project. The team is projected to complete
their tasks on September 5, 2023, but in order to successfully do so they will need an additional
$24,592.58.
Storage
- Omar Patel’s team, is currently also exceeding their allotted budget. The team has used
a total of $7,425 and is projected to incur an additional cost of $5,407.70 before the completion
of the project. The team is projected to complete their tasks on September 4 and will need an
additional $12,832.70.
Off-site Cloud System
- Sara Phan’s team has been successful in staying within their budget.
The team has spent $2,925 so far and is projected to spend an additional $33,097.17. The team is
on track to complete all tasks on November 15, 2023 and will require an additional $36,022.17.
Testing
- Ren Sousa’s team is performing just slightly over budget. They have spent #3,900.00
and will spend another $41,501.63 by the completion of the project. The team is currently
working three days ahead of schedule and is projected to complete all tasks by November 17.
Migration
- Ahmed Williams’ team has not started their tasks yet, due to tasks assigned to other
teams needing to be completed first. With the delay in their start time, the team’s ETC and EAC
are still $14,400.00. The team is projected to complete all of their assigned project tasks by
December 19.
D1. Burndown Chart
PAGE 3
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
MGT2_KKM1: Monitoring and Controlling
Monitoring and Controlling Template
D2. Discussion of Burndown Chart
According to the burndown chart, the project remains encumbered with numerous
outstanding tasks, surpassing those already completed. Notably, on day 18, our progress
exceeded initial projections, evidenced by the completed tasks falling below the expected
trajectory outlined by the orange line.
E. Mitigation Plan
The project is currently ahead of schedule and under budget, as seen in the Earned Value
Analysis and the project Burndown Chart. The project team leaders should use mitigating
strategies in order to ensure everyone stocks to the project's projected completion dates.
The premigration team