Marcus Vinicius A20234 Life Cycle Management Processes Assessment 2
docx
keyboard_arrow_up
School
Maseno University *
*We aren’t endorsed by this school
Course
223
Subject
Information Systems
Date
Nov 24, 2024
Type
docx
Pages
7
Uploaded by BaronAtom394
A20234 Life Cycle Management Processes
Assessment 2
Scenario
You are a project officer working for a construction company. You have been assigned to assist the project manager on a 2-storey house build. The build is expected to be completed in 16 weeks and all tradespeople have been assigned their roles and timelines. The procurement person has been given a list of all the materials that need to be ordered and their delivery due dates. 1.
Update last week’s status report provided below with the following details:
-
Electrician was sick for the week so rough electrical task behind by 1 week
-
Rough Framing tasks completed
-
Rough plumbing completed
-
Windows arrived 2 days late and cost $12500. This has gone over budget by $3500
Project Status Report – Week 2 – 10/03/2022
Project Name:
3 Connor Street, West Sinclair, NSW 2487
Project Manager:
Nathan Miles
Activities Completed This Week
-
Sewer lines installed
-
Foundation poured
-
Framing ordered and arrives Monday
Planned Activities for Next Week
-
Rough framing
-
Rough electrical wiring
-
Rough plumbing
Budget
-
Current spend $120,000 and on budget (no overspend)
Current Risks/Issues
-
Electrician advised he wouldn’t be there Monday due to being ill – could delay project
-
Cost of materials appear to be going up – may impact budget
Project Status Report – Week 3 – 17/03/2022
Project Name: 3 Connor Street, West Sinclair, NSW 2487
Project Manager: Marcus Vinicius
Activities Completed This Week
i.
Sewer lines installed
ii.
Foundation poured
iii.
Rough Framing tasks completed
iv.
Rough Plumbing completed
Activities Behind Schedule
i.
Rough Electrical wiring delayed by 1 week due to the electrician's illness
Newly Identified Issues
i.
Windows arrived 2 days late
ii.
Cost of windows: $12,500 (overspent by $3,500)
Planned Activities for Next Week
i.
Interior work commencement
ii.
Electrical wiring catch-up
iii.
Inspection scheduling
Budget
i.
Current Spend: $135,000 (overspent by $15,000)
ii.
Identified Overspend: Windows ($3,500), Unforeseen Costs ($11,500)
Risks/Issues Update
i.
Electrician's absence affected the rough electrical timeline
ii.
Increased material costs impacting the overall project budget
iii.
Windows delay has caused a budget overrun and potential timeline adjustments
Mitigation Actions
i.
Coordinate with the electrician to expedite the rough electrical tasks
ii.
Evaluate alternative suppliers to control material costs
iii.
Implement schedule adjustments to minimize the impact of delays
2.
Update the work breakdown structure based on the status report above to show the changes to the original baseline
.
2.
Task
Baseline
Actual
Start
End
Start
End
Prepare site
1 March
3 March
1 March
3 March
Sewer lines
6 March
7 March
6 March
7 March
Pour Slab
9 March
9 March
9 March
9 March
Rough Framing
13 March
14 March
13 March
In Progress
Rough Plumbing
13 March
14 March
13 March
In Progress
Rough Electrical
13 March
15 March
Delayed by 1 week
Window Install
14 March
15 March
16 March
In Progress
3.
Assist in undertaking a risk analysis of the risks and issues you have listed in the status report for this week and
add them to the existing risk register below.
Risk Register
Risk Name
Risk Description
Impact on Project
Risk Rating (H,M,L)
Weather
Bad weather prohibits contractors working on building due to safety issues
Delay in house finish date
L
Delivery of materials are delayed
Materials don’t arrive on or before specified date that they are required
Delay in house finish date and possible impact on schedule for contractors and their availability
L
Build approval delayed
Independent certifier not available to inspect and provide approval
Delay in the house being handed over to client and therefore delay in final payment from client
M
Electrician illness
Key electrician being ill and unable to work during the rough electrical phase
Delay in the rough electrical tasks, affecting subsequent project phases
M
Increased material Cost of materials going up impacting Overspending, potential budget M
2
costs
the project budget
overrun, and financial strain
Windows arrival delay
Windows arriving 2 days late and exceeding the budget
Delay in the project timeline, budget overrun, and possible impact on subsequent activities
M
4.
Complete the change request below for the following changes requested by the home owner, Madonna Leonard:
-
Change the tiles for the flooring throughout the house and the new tile will cost and additional $900
-
Change the external house paint colour to Mojave
-
Change the driveway from a stamped concrete driveway to an exposed concrete driveway in salt and pepper colour. Due to additional labour and materials, this will add another $2000 to the cost
Change Request – #3CS005
Project Name:
3 Connor Street, West Sinclair, NSW 2487
Project Manager:
Nathan Miles
Requester: Description of Change 1: Impact of Change 1 on project: Cost of Change 1: Description of Change 2: Impact of Change 2 on project: Cost of Change 2
: Description of Change 2: Impact of Change 2 on project: Cost of Change 2: Project Manager to complete
Status:
Approved / Not Approved
Action to be taken: Change Request – #3CS005 Project Name:
3 Connor Street, West Sinclair, NSW 2487 Project Manager:
Nathan Miles
Requester:
Madonna Leonard
Description of Change 1:
i.
Change: Replace the flooring tiles throughout the house.
ii.
Impact on Project: Aesthetic improvement, potential delay in project timeline.
iii.
Cost of Change 1: Additional $900 for the new tiles.
Description of Change 2:
i.
Change: Change the external house paint colour to Mojave.
ii.
Impact on Project: Aesthetic enhancement, no significant impact on project timeline.
iii.
Cost of Change 2: No additional cost specified.
Description of Change 3:
i.
Change: Change the driveway from stamped concrete to exposed concrete in salt and pepper colour.
3
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
ii.
Impact on Project: Aesthetic alteration, potential delay due to additional labour and materials.
iii.
Cost of Change 3: Additional $2000 for labour and materials.
Project Manager to complete Status: Approved / Not Approved
Action to be taken:
i.
Review the impact and cost of each change.
ii.
Ensure that the changes align with the project timeline and budget.
iii.
Coordinate with relevant teams to implement approved changes promptly.
iv.
Update project documentation to reflect approved changes.
Status:
Approved Action to be taken: Communicate the approved changes to the relevant teams and update project
documentation accordingly. Monitor the impact on the timeline and budget closely.
5.
Create a checklist of at least 5 things that the project manager needs to have ready for the handover to the client. You need to include in your list project documentation eg. final budget, as well as other items that the home owner would need eg. keys, appliance manuals, etc.
House Handover Checklist
Project Name:
3 Connor Street, West Sinclair, NSW 2487
Project Manager:
Nathan Miles
Item/Document for Handover
Who
Complete (Y/N)
Finalized Project Documentation
Project Manager
Keys and Access Information
Project Manager
Appliance Manuals and Warranties
Project Manager
Final Budget and Financial Summary
Project Manager
Completion Certificate and Regulatory Approvals
Project Manager
Signature: Date: 25/11/2023
6
. What financial, legal and contractual obligations must you finalise for your project?
In finalizing the Two-Storey House Build project, several financial, legal, and contractual obligations must be
addressed to ensure a smooth transition and compliance with regulations. Here are the key considerations:
Financial Obligations:
i.
Final Budget Reconciliation: Review and reconcile the final budget to ensure accurate documentation of all
expenditures and costs incurred during the project.
ii.
Invoice Settlement: Ensure that all invoices from suppliers, contractors, and service providers are settled and
paid in accordance with the agreed-upon terms.
iii.
Budget Reporting: Provide a comprehensive budget report to the client, detailing the initial budget, any
variations, and the final project costs.
4
iv.
Financial Auditing
:
Conduct a financial audit to verifying all financial transactions and expenses are
accounted for correctly as advices Tinsley, (2022).
Legal Obligations:
i.
Regulatory Compliance: Ensure that the construction project complies with all local building codes, zoning
regulations, and other legal requirements.
ii.
Certificates and Approvals: Obtain and organize all necessary certificates and approvals, including the
completion certificate and any additional permits required for the project.
iii.
Warranty Documentation: Compile and provide documentation for any warranties associated with materials,
workmanship, or installed systems within the house.
iv.
Defects Liability Period: Ensure compliance with the defects liability period, addressing and rectifying any
defects identified during the agreed-upon period.
Contractual Obligations:
i.
Contract
Closure
:
Officially close out contracts with suppliers, contractors, and other stakeholders, confirming
the successful completion of their respective obligations.
ii.
Final Project Review with Stakeholders: Conduct a final project review with all stakeholders to ensure that all
contractual obligations have been met and that there are no outstanding issues.
iii.
Handover Documentation: Prepare and organize all documentation required for the handover process,
including completion certificates, as-built drawings, and any relevant project records.
iv.
Client Sign-Off: Obtain formal sign-off from the client to acknowledge the successful completion of the
project and their satisfaction with the final deliverables.
v.
Legal Release Documents: Ensure that all necessary legal release documents are prepared and signed,
officially releasing the construction company from any further contractual obligations related to the project.
7. Provide 3 suggestions and explain how they could improve the project performance in the future.
i.
Continuous Stakeholder Communication: Establish a more comprehensive and regular communication plan
keeping all stakeholders, including the client, informed about project progress, challenges, and any deviations
from the original plan. Implement regular check-ins, progress reports, and transparent communication
channels to foster a collaborative and informed project environment. Improved communication helps
manage expectations, reduces uncertainties, and enhances stakeholder satisfaction. A well-informed client is
more likely to understand and support adjustments to the project plan, fostering a positive working
relationship and minimizing misunderstandings.
ii.
Enhanced Contingency Planning: Incorporate a more robust contingency planning strategy to address
unexpected events such as the illness of a key team member or delays in material delivery. This will involve as
Brooks and Curnin, (2021) say creating alternative schedules, identifying backup resources, and regularly
reviewing and updating the contingency plan to adapt to evolving project circumstances. By proactively
anticipating potential risks and disruptions, the project team will respond more effectively when unexpected
challenges arise. This ensures timelines are not unduly impacted and allows for quicker recovery from
setbacks, ultimately enhancing project resilience and performance.
iii.
Technology Integration for Project Monitoring: Integrate advanced project management tools and technology
for real-time monitoring and reporting. Implementing a cloud-based project management system providing
instant updates on timelines, resource allocation, and budget tracking can significantly improve visibility and
decision-making. Leveraging technology allows for more accurate and timely project monitoring, enabling the
project manager to identify potential issues before they escalate. Real-time data accessibility enhances the
ability to make informed decisions, streamline processes, and improve overall project efficiency.
8. Review the project performance based on all the information provided in questions 1 – 4 and explain at least 2 lessons learned.
Lesson Learned 1: Proactive Contingency Planning is Crucial
The project encountered delays due to the electrician's unexpected illness, impacting the rough electrical tasks. This
underscores the importance of proactive contingency planning. A lesson learned is having contingency plans in place
for key resources says Meng, (2020). such as identifying backup electricians or having a flexible schedule, will mitigate
the impact of unforeseen events. Moving forward, the project team ought to enhance contingency plans to address
potential disruptions, ensuring a more resilient project timeline.
5
Lesson Learned 2: Continuous Monitoring of Supplier Performance is Essential
The delayed arrival of windows and the associated budget overrun highlight the significance of continuous
monitoring of supplier performance. A lesson learned is the need for a robust supplier management system.
Regularly assessing supplier reliability and implementing measures, such as monitoring delivery schedules and having
alternative suppliers, minimizes the risk of delays and budget overruns. This lesson emphasizes the importance of
maintaining proactive communication and relationships with suppliers throughout the project life cycle.
6
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
References:
Tinsley, R. (2022).
Advanced Project Financing Structuring Risk
. Euromoney Institutional Investor PLC.
Brooks, B., & Curnin, S. (2021). Stretch
‐
Thinking Loops: A New Technique for Scenario Planning.
Risk, Hazards & Crisis in Public Policy
,
12
(1), 110-124.
Meng, X. (2020). Proactive management in the context of construction supply chains.
Production Planning & Control
,
31
(7), 527-539.
7