Assignment 2: Project Schedules Instructions Please read and follow the instructions carefully. Failure to do so will result in a penalty to the to the evaluation. 1. Provide a title page with the title of the assignment, your full name, student ID, George Brown email address and date. 2. Provide a summary page (separate and distinct from the any rough work). a. The summary page must provide the final answer to each question ONLY. No calculations and/or rough work should be part of the summary page. b. The answers must be clearly numbered and are aligned with the order of the questions presented below. The answer must be clearly visible / highlighted. 3. Provide an appendix with all rough work / calculations. You must show your work. IF you are using excel or word for your calculations, the file must be provided. You can attach a screenshot of the file page(s); however, you must also upload the original file as well. Clearly title each file with the name of the assignment AND your name (first / last). 4. Provide in the appendix all the relevant MS Project items. a. Attach a screen shot of each MS Project Scenarios (the original scenario each subsequent variation as well). b. You must also attach the original .mpp file(s) as well. Clearly title each file with the name of the scenario AND your name (first / last). The instructor may use this file to check and validate the work submitted is the students own work and ensure that the xl is properly set up with the functions. 5. If the assignment is submitted without the rough work / calculations / xl file, a 50% penalty will be applied to the final evaluation. 6. All files MUST be submitted within D2L. No emailed submissions will be accepted. This is not negotiable. 7. Late assignments will be assessed a point deduction (from the total points available) per day for every day late past the due date. 8. Please ensure all work completed is your own work. Plagiarism is not acceptable. If determined work submitted is not your own, a possible mark of 0 will be assigned. 9. Total marks (points): a. 60 i. 30 marks for the completed questions (summary page) ii. 30 marks for the attached and completed work (rough work / calculations 10. The assignment is worth 4.5% of your overall mark. 11. This assignment is to be completed and submitted individually.
Scenario: Network Diagram for a Small Project Activity Initial Node Final Node Estimated Duration (Days) A 1 2 2 B 2 3 3 C 2 4 3 D 2 5 2 E 3 6 4 F 4 6 3 G 5 7 6 H 6 8 2 I 7 8 3 J 8 9 4 K 7 10 5 L 7 11 2 M 10 9 3 N 9 12 3 O 10 13 3 P 11 13 7 Questions: Question 1. (5 marks)
a) Using the information provided in the table above, draw the AOA network diagram representing the project. Put the node numbers in the circle and draw arrows from node to node, labelling each arrow with the activity letter and estimated time. b) Identify all the paths on the network diagram. Calculate the estimated duration of each path. c) What is the critical path for this project and how long is it? d) What is the shortest possible time it will take the project to complete? Question 2. Using the Network Diagram (from above), fill in the table for each activity. (8 marks) Use the following Table format to summarize your answers. You will need to exoand the table to list all activities. Please use the same order as above: A, B, C, etc. for the rows. NOTE, this table will be on your summary page. However, you must provide all the relevant information for your network diagram in the appendix. You must show each of the values for each activity in on the network diagram. Activity Early Start (ES) Early Finish (EF) Late Start (LS) Late Finish (LF) Free Float (FF) Total Float (TF) A B etc. Question 3. Using the information for the small project in the first table above, create the project within MS Project. Once you have created the original project, make the following changes, and answer the applicable questions. ALL these scenarios are to be modeled in MS Project with applicable screen shots for each of the scenarios (original, change a), change b), and change c)) provided in your submission (appendix) as well as the .mpp file for the initial network diagram. (12 Marks) a) The duration for activity I is extended, and the new estimate is I = 5 days . What is the impact to the critical path and/or the critical path duration (if any)? b) Revert to the initial state (original network diagram and reset I = 3 days). Now, the duration for activity D is extended, and the new estimate is D = 4 days . What is the impact to the critical path and/or the critical path duration (if any)? c) Revert to the initial state (original network diagram and reset D = 2 days). The project team had a change order that resulted in descoping of activity I from the project. What is the impact to the critical path and/or the critical path duration (if any)?