assignment 1 instructions

docx

School

University of Windsor *

*We aren’t endorsed by this school

Course

3310

Subject

Industrial Engineering

Date

Dec 6, 2023

Type

docx

Pages

2

Uploaded by PresidentTroutPerson816

Report
Assignment 1 Note: All assignments must be typed in Microsoft Word and submitted online ( without the questions ) through the course website on Bright Space. Assignments submitted in formats other than Microsoft Word will not be graded. Charts and diagrams can be drawn by hand and then their pictures be copied into the Word document. The answers to all questions should be submitted in a single document. Late assignments will not be accepted. Each assignment should be your own work. All submitted assignments will be compared against the existing works or sources by Turnitin software to examine the originality of your assignment and identify areas of overlap. SafeAssign originality reports provide detailed information about the matches found between a submitted assignment and existing works. Identical assignments will be given a grade of zero. 1) Marjatta Viitasalo operates a bakery in Thunder Bay, Ontario. Because of its excellent product and excellent location, demand has increased by 42.6% in the last year. On far too many occasions, customers have not been able to purchase the bread of their choice. Because of the size of the store, no new ovens can be added. At a staff meeting, one employee suggested ways to load the ovens differently so that more loaves of bread can be baked at one time. This new process will require that the ovens be loaded by hand, requiring additional manpower. This is the only thing to be changed. If the bakery makes 1500 loaves per month with a labour productivity of 2 loaves per labour-hour, how many workers will Viitasalo need to add? (Hint: Each employee works 160 hours per month.) 2) The City of Lethbridge has decided to build a botanical garden and picnic area in the heart of the city for the recreation of its citizens. The precedence table for all the activities required to construct this area successfully is given below. Draw the Gantt chart for the whole construction activity. Cod Activity Description Time (in hours) Immediate Predecessor(s) A Planning Find location; determine resource requirements 20 None B Purchasing Requisition of lumber and sand 80 Planning C Excavation Dig and grade 80 Planning D Sawing Saw lumber into appropriate sizes 30 Purchasing E Placement Position lumber in correct locations 20 Sawing, excavation F Assembly Nail lumber together 10 Placement G Infill Put sand in and under the equipment 20 Assembly H Outfill Put dirt around the equipment 10 Assembly I Decoration Put grass all over the garden, landscape, paint 30 Infill, outfill
Assignment 1 3) McGee Carpet and Trim installs carpet in commercial offices. Andrea McGee has been very concerned with the amount of time it took to complete several recent jobs. Some of her workers are very unreliable. A list of activities and their optimistic completion time, the most likely completion time, and the pessimistic completion time (all in days) for a new contract are given in the following table: a) Determine the expected completion time and variance for each activity. b) Determine the total project completion time and the critical path for the project. c) Determine ES, EF, LS, LF, and slack for each activity. d) What is the probability that McGee Carpet and Trim will finish the project in 50 days or less? 4) Bolling Electronics manufactures DVD players for commercial use. W. Blaker Bolling, president of Bolling Electronics, is contemplating producing DVD players for home use. The activities necessary to build an experimental model and related data are given in the following table: Activit y Normal Time (weeks) Crash Time (weeks) Normal Cost ($) Crash Immediate Cost ($) Predecessor(s) A 3 2 1000 1600 B 2 1 2000 2700 C 11 1 300 500 D 7 3 1300 1600 A E 6 3 850 1000 B F 2 1 4000 5000 C G 4 2 1500 2000 D, E a) What is the project completion date? b) Crash this project to 10 weeks at the least cost. c) Crash this project to seven weeks at the least cost. Activity a Time (days) m b Immediate Predecessor(s) A 3 6 8 B 2 4 4 C 1 2 3 D 6 7 8 C E 2 4 6 B, D F 6 10 14 A, E G 1 2 4 A, E H 3 6 9 F I 10 11 12 G J 14 16 20 C K 2 8 10 H, I
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
  • Access to all documents
  • Unlimited textbook solutions
  • 24/7 expert homework help