You have signed a contract to build a garage for the Simpsons. You will receive a $500 bonus for completing the project within 21 days, The contract also cantains a penalty clause in which you will lose $100 for each day the project takes longer than the agreed 21 days. Draw a project network given the information below. Then, do the following: . Complete the forward and backward pass . Determine the critical path 'y . Compute the Total slack for all activities s\.‘(‘)' Determine which activities have free float AY ) Activity e \3 Predec Prepare Site N Pour Foundation (_)O Erect Frame § Roof O Je; Windows / Qfl \& Doors \\(\ (*.& \(p Electrical Q}\(\ \\..{\' Rough-In Frame 0}(- Door Opener Paint Clean Up What is the free float of the activity "doors”, with the successor activity "door opener"? AT T TOMMODO® P gerwNE = = ——IMmMopOoONANAm» - 1. 1 day | 74 zero days 4 3 days v 4. 2 days
Discover more documents: Sign up today!
Unlock a world of knowledge! Explore tailored content for a richer learning experience. Here's what you'll get:
  • Access to all documents
  • Unlimited textbook solutions
  • 24/7 expert homework help