Exam 2
docx
keyboard_arrow_up
School
Angelo State University *
*We aren’t endorsed by this school
Course
MISC
Subject
Accounting
Date
Feb 20, 2024
Type
docx
Pages
21
Uploaded by ProfessorArmadilloPerson1008
QUESTION 1
1.
THE FOLLOWING INFORMATION IS USED FOR QUESTIONS 1 – 11.
Test Company uses a normal, job-order cost system to determine product cost. The following jobs were in process on July 1.
Job 603
Job 604
Job 605
Direct materials
$1,600
$1,200
$800
Direct labor
2,000
1,500
1,000
Applied overhead
1,500
1,125
750
During July, Test Company completed Jobs 603 and 604 and began production on Jobs 701 and 702. Jobs 605, 701, and 702 were still in process on July 31. There was on finished goods inventory on July 1. Test Company delivered Job 603 and billed the customer for cost plus 20%.
The following costs were added to production during July.
Job 603
Job 604
Job 605
Job 701
Job 702
Direct materials
$850
$1,000
$1,200
$650
$500
Direct labor
1,000
1,500
1,600
800
600
Applied overhead
750
1,125
1,200
600
450
Actual overhead cost for July totaled $4,250. The overhead variance is considered immaterial.
Determine the balance of work-in-process inventory as of July 31.
Note: Give your answer using dollar signs and commas but no decimal points (cents).
Example: $12,345
4 points QUESTION 2
1.
THE FOLLOWING INFORMATION IS USED FOR QUESTIONS 1 – 11.
Test Company uses a normal, job-order cost system to determine product cost. The following jobs were in process on July 1.
Job 603
Job 604
Job 605
Direct materials
$1,600
$1,200
$800
Direct labor
2,000
1,500
1,000
Applied overhead
1,500
1,125
750
During July, Test Company completed Jobs 603 and 604 and began production on Jobs 701 and 702. Jobs 605, 701, and 702 were still in process on July 31. There was on finished goods inventory on July 1. Test Company delivered Job 603 and billed the customer for cost plus 20%.
The following costs were added to production during July.
Job 603
Job 604
Job 605
Job 701
Job 702
Direct materials
$850
$1,000
$1,200
$650
$500
Direct labor
1,000
1,500
1,600
800
600
Applied overhead
750
1,125
1,200
600
450
Actual overhead cost for July totaled $4,250. The overhead variance is considered immaterial.
Determine the cost of goods manufactured for July.
Note: Give your answer using dollar signs and commas but no decimal points (cents).
Example: $12,345
4 points QUESTION 3
1.
THE FOLLOWING INFORMATION IS USED FOR QUESTIONS 1 – 11.
Test Company uses a normal, job-order cost system to determine product cost. The following jobs were in process on July 1.
Job 603
Job 604
Job 605
Direct materials
$1,600
$1,200
$800
Direct labor
2,000
1,500
1,000
Applied overhead
1,500
1,125
750
During July, Test Company completed Jobs 603 and 604 and began production on Jobs 701 and 702. Jobs 605, 701, and 702 were still in process on July 31. There was on finished goods inventory on July 1. Test Company delivered Job 603 and billed the customer for cost plus 20%.
The following costs were added to production during July.
Job 603
Job 604
Job 605
Job 701
Job 702
Direct materials
$850
$1,000
$1,200
$650
$500
Direct labor
1,000
1,500
1,600
800
600
Applied overhead
750
1,125
1,200
600
450
Actual overhead cost for July totaled $4,250. The overhead variance is considered immaterial.
Determine the balance of finished goods inventory as of July 31.
Note: Give your answer using dollar signs and commas but no decimal points (cents).
Example: $12,345
4 points QUESTION 4
1.
THE FOLLOWING INFORMATION IS USED FOR QUESTIONS 1 – 11.
Test Company uses a normal, job-order cost system to determine product cost. The following jobs were in process on July 1.
Job 603
Job 604
Job 605
Direct materials
$1,600
$1,200
$800
Direct labor
2,000
1,500
1,000
Applied overhead
1,500
1,125
750
During July, Test Company completed Jobs 603 and 604 and began production on Jobs 701 and 702. Jobs 605, 701, and 702 were still in process on July 31. There was on finished goods inventory on July 1. Test Company delivered Job 603 and billed the customer for cost plus 20%.
The following costs were added to production during July.
Job 603
Job 604
Job 605
Job 701
Job 702
Direct materials
$850
$1,000
$1,200
$650
$500
Direct labor
1,000
1,500
1,600
800
600
Applied overhead
750
1,125
1,200
600
450
Actual overhead cost for July totaled $4,250. The overhead variance is considered immaterial.
Determine cost of goods sold for July before adjusting for the overhead variance.
Note: Give your answer using dollar signs and commas but no decimal points (cents).
Example: $12,345
4 points QUESTION 5
1.
THE FOLLOWING INFORMATION IS USED FOR QUESTIONS 1 – 11.
Test Company uses a normal, job-order cost system to determine product cost. The following jobs were in process on July 1.
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
Job 603
Job 604
Job 605
Direct materials
$1,600
$1,200
$800
Direct labor
2,000
1,500
1,000
Applied overhead
1,500
1,125
750
During July, Test Company completed Jobs 603 and 604 and began production on Jobs 701 and 702. Jobs 605, 701, and 702 were still in process on July 31. There was on finished goods inventory on July 1. Test Company delivered Job 603 and billed the customer for cost plus 20%.
The following costs were added to production during July.
Job 603
Job 604
Job 605
Job 701
Job 702
Direct materials
$850
$1,000
$1,200
$650
$500
Direct labor
1,000
1,500
1,600
800
600
Applied overhead
750
1,125
1,200
600
450
Actual overhead cost for July totaled $4,250. The overhead variance is considered immaterial.
Determine cost of goods sold for July after adjusting for the overhead variance.
Note: Give your answer using dollar signs and commas but no decimal points (cents).
Example: $12,345
4 points QUESTION 6
1.
THE FOLLOWING INFORMATION IS USED FOR QUESTIONS 1 – 11.
Test Company uses a normal, job-order cost system to determine product cost. The following jobs were in process on July 1.
Job 603
Job 604
Job 605
Direct materials
$1,600
$1,200
$800
Direct labor
2,000
1,500
1,000
Applied overhead
1,500
1,125
750
During July, Test Company completed Jobs 603 and 604 and began production on Jobs 701 and 702. Jobs 605, 701, and 702 were still in process on July 31. There was on finished goods inventory on July 1. Test Company delivered Job 603 and billed the customer for cost plus 20%.
The following costs were added to production during July.
Job 603
Job 604
Job 605
Job 701
Job 702
Direct materials
$850
$1,000
$1,200
$650
$500
Direct labor
1,000
1,500
1,600
800
600
Applied overhead
750
1,125
1,200
600
450
Actual overhead cost for July totaled $4,250. The overhead variance is considered immaterial.
The journal entry to record the materials requisitioned for Job 603 in July would include
A debit to cost of goods manufactured (Job 603) for $850
A debit to direct materials used (Job 603) for $850
A debit to work-in-process inventory (Job 603) for $850
A debit to raw materials inventory (Job 603) for $850
4 points QUESTION 7
1.
THE FOLLOWING INFORMATION IS USED FOR QUESTIONS 1 – 11.
Test Company uses a normal, job-order cost system to determine product cost. The following jobs were in process on July 1.
Job 603
Job 604
Job 605
Direct materials
$1,600
$1,200
$800
Direct labor
2,000
1,500
1,000
Applied overhead
1,500
1,125
750
During July, Test Company completed Jobs 603 and 604 and began production on Jobs 701 and 702. Jobs 605, 701, and 702 were still in process on July 31. There was on finished goods inventory on July 1. Test Company delivered Job 603 and billed the customer for cost plus 20%.
The following costs were added to production during July.
Job 603
Job 604
Job 605
Job 701
Job 702
Direct materials
$850
$1,000
$1,200
$650
$500
Direct labor
1,000
1,500
1,600
800
600
Applied overhead
750
1,125
1,200
600
450
Actual overhead cost for July totaled $4,250. The overhead variance is considered immaterial.
The journal entry to record the direct labor cost for Job 603 in July would include
A debit to work-in-process inventory (Job 603) for $1,000
A debit to wages expense (Job 603) for $1,000
A debit to cost of goods manufactured (Job 603) for $1,000
A debit to direct labor (Job 603) for $1,000
4 points QUESTION 8
1.
THE FOLLOWING INFORMATION IS USED FOR QUESTIONS 1 – 11.
Test Company uses a normal, job-order cost system to determine product cost. The following jobs were in process on July 1.
Job 603
Job 604
Job 605
Direct materials
$1,600
$1,200
$800
Direct labor
2,000
1,500
1,000
Applied overhead
1,500
1,125
750
During July, Test Company completed Jobs 603 and 604 and began production on Jobs 701 and 702. Jobs 605, 701, and 702 were still in process on July 31. There was on finished goods inventory on July 1. Test Company delivered Job 603 and billed the customer for cost plus 20%.
The following costs were added to production during July.
Job 603
Job 604
Job 605
Job 701
Job 702
Direct materials
$850
$1,000
$1,200
$650
$500
Direct labor
1,000
1,500
1,600
800
600
Applied overhead
750
1,125
1,200
600
450
Actual overhead cost for July totaled $4,250. The overhead variance is considered immaterial.
The journal entry to record the overhead applied to Job 603 in July would include
A debit to cost of goods manufactured for $750
A debit to overhead control for (Job 603) for $750
A debit to various overhead cost accounts (Job 603) for $750
A debit to work-in-process inventory (Job 603) for $750
4 points QUESTION 9
1.
THE FOLLOWING INFORMATION IS USED FOR QUESTIONS 1 – 11.
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
Test Company uses a normal, job-order cost system to determine product cost. The following jobs were in process on July 1.
Job 603
Job 604
Job 605
Direct materials
$1,600
$1,200
$800
Direct labor
2,000
1,500
1,000
Applied overhead
1,500
1,125
750
During July, Test Company completed Jobs 603 and 604 and began production on Jobs 701 and 702. Jobs 605, 701, and 702 were still in process on July 31. There was on finished goods inventory on July 1. Test Company delivered Job 603 and billed the customer for cost plus 20%.
The following costs were added to production during July.
Job 603
Job 604
Job 605
Job 701
Job 702
Direct materials
$850
$1,000
$1,200
$650
$500
Direct labor
1,000
1,500
1,600
800
600
Applied overhead
750
1,125
1,200
600
450
Actual overhead cost for July totaled $4,250. The overhead variance is considered immaterial.
The journal entry to record the completion of Job 603 would include
A debit to work-in-process inventory (Job 603) for $2,600
A debit to cost of goods manufactured (Job 603) for $7,700
A debit to finished goods inventory (Job 603) for $2,600
A debit to finished goods inventory(Job 603) for $7,700
4 points QUESTION 10
1.
THE FOLLOWING INFORMATION IS USED FOR QUESTIONS 1 – 11.
Test Company uses a normal, job-order cost system to determine product cost. The following jobs were in process on July 1.
Job 603
Job 604
Job 605
Direct materials
$1,600
$1,200
$800
Direct labor
2,000
1,500
1,000
Applied overhead
1,500
1,125
750
During July, Test Company completed Jobs 603 and 604 and began production on Jobs 701 and 702. Jobs 605, 701, and 702 were still in process on July 31. There was on finished goods inventory on July 1. Test Company delivered Job 603 and billed the customer for cost plus 20%.
The following costs were added to production during July.
Job 603
Job 604
Job 605
Job 701
Job 702
Direct materials
$850
$1,000
$1,200
$650
$500
Direct labor
1,000
1,500
1,600
800
600
Applied overhead
750
1,125
1,200
600
450
Actual overhead cost for July totaled $4,250. The overhead variance is considered immaterial.
The journal entry to record the sale of Job 603 would include
A debit to sales for $7,700
A debit to finished goods inventory (Job 603) for $2,600
A debit to accounts receivable for $9,240
A debit to cost of goods sold for $3,120
4 points QUESTION 11
1.
THE FOLLOWING INFORMATION IS USED FOR QUESTIONS 1 – 11.
Test Company uses a normal, job-order cost system to determine product cost. The following jobs were in process on July 1.
Job 603
Job 604
Job 605
Direct materials
$1,600
$1,200
$800
Direct labor
2,000
1,500
1,000
Applied overhead
1,500
1,125
750
During July, Test Company completed Jobs 603 and 604 and began production on Jobs 701 and 702. Jobs 605, 701, and 702 were still in process on July 31. There was on finished goods inventory on July 1. Test Company delivered Job 603 and billed the customer for cost plus 20%.
The following costs were added to production during July.
Job 603
Job 604
Job 605
Job 701
Job 702
Direct materials
$850
$1,000
$1,200
$650
$500
Direct labor
1,000
1,500
1,600
800
600
Applied overhead
750
1,125
1,200
600
450
Actual overhead cost for July totaled $4,250. The overhead variance is considered immaterial.
The journal entry to record the actual overhead cost for July would include
A credit to overhead control for $4,250
A debit to overhead variance for $125
A debit to overhead control for $4,250
A debit to work-in-process inventory for $4,250
4 points QUESTION 12
1.
Test Company reported the following costs for Job 101.
Job 101
Direct materials
$2,500
Direct labor
1,500
Applied overhead
1,000
Overhead is applied at a rate of $10 per direct labor hour.
Quality inspection showed three units in the job to be defective. The units were reworked using additional direct materials of $100 and additional direct labor of five hours at a cost of $75. The rework is considered normal spoilage.
Determine the total cost of Job 101.
Note: Give your answer using dollar signs and commas but no decimal points (cents).
Example: $12,345
4 points QUESTION 13
1.
Test Company uses a normal, process costing system to determine product cost. The company reported the following production activity in Department 2 for July.
Work-in-process inventory, July 1
1,000 units
Units transferred in from Department 1
8,000 units
Units completed and transferred to finished goods
6,500 units
Determine the number of units in work-in-process inventory in Department 2 as of July 31.
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
Note: Give your answer using commas. Do not include the word “units.”
Example: 12,345
4 points QUESTION 14
1.
Test Company uses a normal, process costing system to determine product cost. The company reported the following production activity in Department 2 for July.
Work-in-process inventory, July 1
1,000 units
Units transferred in from Department 1
8,000 units
Units completed and transferred to finished goods
6,500 units
Determine the number of units started and completed in Department 2 in July.
Note: Give your answer using commas. Do not include the word “units.”
Example: 12,345
4 points QUESTION 15
1.
THE FOLLOWING INFORMATION IS USED FOR QUESTIONS 15 – 25.
Test Company uses a normal, process costing system to determine product cost. The company uses the first-in, first-out (FIFO) method to account for equivalent units and costs in beginning work-in-process.
The product passes through two departments: Department 1 and Department 2. In Department 2, all direct materials are added at the beginning of the process. The following information is available for Department 2 in July.
Work-in-process, July 1
Units
5,000 units
Costs
Direct materials
$25,000
Conversion cost
16,000
Transferred-in cost
20,000
July activity
Units
Transferred in
50,000 units
Completed and transferred out
45,000 units
Costs added
Direct materials
$400,000
Conversion cost
184,000
Transferred-in-cost
200,000
Percentage of completion
Work-in-process, July 1
60%
Work-in-process, July 31
40%
Determine the number of units to account for from the July production report.
Note: Give your answer using commas. Do not include the word “units.”
Example: 12,345
4 points QUESTION 16
1.
THE FOLLOWING INFORMATION IS USED FOR QUESTIONS 15 – 25.
Test Company uses a normal, process costing system to determine product cost. The company uses the first-in, first-out (FIFO) method to account for equivalent units and costs in beginning work-in-process.
The product passes through two departments: Department 1 and Department 2. In Department 2, all direct materials are added at the beginning of the process. The following information is available for Department 2 in July.
Work-in-process, July 1
Units
5,000 units
Costs
Direct materials
$25,000
Conversion cost
16,000
Transferred-in cost
20,000
July activity
Units
Transferred in
50,000 units
Completed and transferred out
45,000 units
Costs added
Direct materials
$400,000
Conversion cost
184,000
Transferred-in-cost
200,000
Percentage of completion
Work-in-process, July 1
60%
Work-in-process, July 31
40%
Determine the equivalent units of output with respect to direct materials for July.
Note: Give your answer using commas. Do not include the word “units.”
Example: 12,345
4 points QUESTION 17
1.
THE FOLLOWING INFORMATION IS USED FOR QUESTIONS 15 – 25.
Test Company uses a normal, process costing system to determine product cost. The company uses the first-in, first-out (FIFO) method to account for equivalent units and costs in beginning work-in-process.
The product passes through two departments: Department 1 and Department 2. In Department 2, all direct materials are added at the beginning of the process. The following information is available for Department 2 in July.
Work-in-process, July 1
Units
5,000 units
Costs
Direct materials
$25,000
Conversion cost
16,000
Transferred-in cost
20,000
July activity
Units
Transferred in
50,000 units
Completed and transferred out
45,000 units
Costs added
Direct materials
$400,000
Conversion cost
184,000
Transferred-in-cost
200,000
Percentage of completion
Work-in-process, July 1
60%
Work-in-process, July 31
40%
Determine the equivalent units of output with respect to conversion cost for July.
Note: Give your answer using commas. Do not include the word “units.”
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
Example: 12,345
4 points QUESTION 18
1.
THE FOLLOWING INFORMATION IS USED FOR QUESTIONS 15 – 25.
Test Company uses a normal, process costing system to determine product cost. The company uses the first-in, first-out (FIFO) method to account for equivalent units and costs in beginning work-in-process.
The product passes through two departments: Department 1 and Department 2. In Department 2, all direct materials are added at the beginning of the process. The following information is available for Department 2 in July.
Work-in-process, July 1
Units
5,000 units
Costs
Direct materials
$25,000
Conversion cost
16,000
Transferred-in cost
20,000
July activity
Units
Transferred in
50,000 units
Completed and transferred out
45,000 units
Costs added
Direct materials
$400,000
Conversion cost
184,000
Transferred-in-cost
200,000
Percentage of completion
Work-in-process, July 1
60%
Work-in-process, July 31
40%
Determine the equivalent units of output with respect to transferred-in cost for July.
Note: Give your answer using commas. Do not include the word “units.”
Example: 12,345
4 points
QUESTION 19
1.
THE FOLLOWING INFORMATION IS USED FOR QUESTIONS 15 – 25.
Test Company uses a normal, process costing system to determine product cost. The company uses the first-in, first-out (FIFO) method to account for equivalent units and costs in beginning work-in-process.
The product passes through two departments: Department 1 and Department 2. In Department 2, all direct materials are added at the beginning of the process. The following information is available for Department 2 in July.
Work-in-process, July 1
Units
5,000 units
Costs
Direct materials
$25,000
Conversion cost
16,000
Transferred-in cost
20,000
July activity
Units
Transferred in
50,000 units
Completed and transferred out
45,000 units
Costs added
Direct materials
$400,000
Conversion cost
184,000
Transferred-in-cost
200,000
Percentage of completion
Work-in-process, July 1
60%
Work-in-process, July 31
40%
Determine the cost per equivalent unit with respect to direct materials for July.
Note: Give your answer using dollar signs and carry your answer to the nearest cent.
Examples: $12.34 or $12.00
4 points QUESTION 20
1.
THE FOLLOWING INFORMATION IS USED FOR QUESTIONS 15 – 25.
Test Company uses a normal, process costing system to determine product cost. The company uses the first-in, first-out (FIFO) method to account for equivalent units and costs in beginning work-in-process.
The product passes through two departments: Department 1 and Department 2. In Department 2, all direct materials are added at the beginning of the process. The following information is available for Department 2 in July.
Work-in-process, July 1
Units
5,000 units
Costs
Direct materials
$25,000
Conversion cost
16,000
Transferred-in cost
20,000
July activity
Units
Transferred in
50,000 units
Completed and transferred out
45,000 units
Costs added
Direct materials
$400,000
Conversion cost
184,000
Transferred-in-cost
200,000
Percentage of completion
Work-in-process, July 1
60%
Work-in-process, July 31
40%
Determine the cost per equivalent unit with respect to conversion cost for July.
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
Note: Give your answer using dollar signs and carry your answer to the nearest cent.
Examples: $12.34 or $12.00
4 points QUESTION 21
1.
THE FOLLOWING INFORMATION IS USED FOR QUESTIONS 15 – 25.
Test Company uses a normal, process costing system to determine product cost. The company uses the first-in, first-out (FIFO) method to account for equivalent units and costs in beginning work-in-process.
The product passes through two departments: Department 1 and Department 2. In Department 2, all direct materials are added at the beginning of the process. The following information is available for Department 2 in July.
Work-in-process, July 1
Units
5,000 units
Costs
Direct materials
$25,000
Conversion cost
16,000
Transferred-in cost
20,000
July activity
Units
Transferred in
50,000 units
Completed and transferred out
45,000 units
Costs added
Direct materials
$400,000
Conversion cost
184,000
Transferred-in-cost
200,000
Percentage of completion
Work-in-process, July 1
60%
Work-in-process, July 31
40%
Determine the cost per equivalent unit with respect to transferred-in cost for July.
Note: Give your answer using dollar signs and carry your answer to the nearest cent.
Examples: $12.34 or $12.00
4 points QUESTION 22
1.
THE FOLLOWING INFORMATION IS USED FOR QUESTIONS 15 – 25.
Test Company uses a normal, process costing system to determine product cost. The company uses the first-in, first-out (FIFO) method to account for equivalent units and costs in beginning work-in-process.
The product passes through two departments: Department 1 and Department 2. In Department 2, all direct materials are added at the beginning of the process. The following information is available for Department 2 in July.
Work-in-process, July 1
Units
5,000 units
Costs
Direct materials
$25,000
Conversion cost
16,000
Transferred-in cost
20,000
July activity
Units
Transferred in
50,000 units
Completed and transferred out
45,000 units
Costs added
Direct materials
$400,000
Conversion cost
184,000
Transferred-in-cost
200,000
Percentage of completion
Work-in-process, July 1
60%
Work-in-process, July 31
40%
Determine the total cost transferred out for July.
Note: Give your answer using dollars signs and commas but not decimal points (cents).
Example: $12,345
4 points
QUESTION 23
1.
THE FOLLOWING INFORMATION IS USED FOR QUESTIONS 15 – 25.
Test Company uses a normal, process costing system to determine product cost. The company uses the first-in, first-out (FIFO) method to account for equivalent units and costs in beginning work-in-process.
The product passes through two departments: Department 1 and Department 2. In Department 2, all direct materials are added at the beginning of the process. The following information is available for Department 2 in July.
Work-in-process, July 1
Units
5,000 units
Costs
Direct materials
$25,000
Conversion cost
16,000
Transferred-in cost
20,000
July activity
Units
Transferred in
50,000 units
Completed and transferred out
45,000 units
Costs added
Direct materials
$400,000
Conversion cost
184,000
Transferred-in-cost
200,000
Percentage of completion
Work-in-process, July 1
60%
Work-in-process, July 31
40%
Determine the total cost of work-in-process inventory as of July 31.
Note: Give your answer using dollars signs and commas but not decimal points (cents).
Example: $12,345
4 points QUESTION 24
1.
THE FOLLOWING INFORMATION IS USED FOR QUESTIONS 15 – 25.
Test Company uses a normal, process costing system to determine product cost. The company uses the first-in, first-out (FIFO) method to account for equivalent units and costs in beginning work-in-process.
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
The product passes through two departments: Department 1 and Department 2. In Department 2, all direct materials are added at the beginning of the process. The following information is available for Department 2 in July.
Work-in-process, July 1
Units
5,000 units
Costs
Direct materials
$25,000
Conversion cost
16,000
Transferred-in cost
20,000
July activity
Units
Transferred in
50,000 units
Completed and transferred out
45,000 units
Costs added
Direct materials
$400,000
Conversion cost
184,000
Transferred-in-cost
200,000
Percentage of completion
Work-in-process, July 1
60%
Work-in-process, July 31
40%
The journal entry to record the direct materials cost added in July would include
A debit to work-in-process inventory (Department 2) for $425,000
No entry would be required
A debit to work-in-process inventory (Department 2) for $400,000
A debit to raw materials inventory for $400,000
4 points
QUESTION 25
1.
THE FOLLOWING INFORMATION IS USED FOR QUESTIONS 15 – 25.
Test Company uses a normal, process costing system to determine product cost. The company uses the first-in, first-out (FIFO) method to account for equivalent units and costs in beginning work-in-process.
The product passes through two departments: Department 1 and Department 2. In Department 2, all direct materials are added at the beginning of the process. The following information is available for Department 2 in July.
Work-in-process, July 1
Units
5,000 units
Costs
Direct materials
$25,000
Conversion cost
16,000
Transferred-in cost
20,000
July activity
Units
Transferred in
50,000 units
Completed and transferred out
45,000 units
Costs added
Direct materials
$400,000
Conversion cost
184,000
Transferred-in-cost
200,000
Percentage of completion
Work-in-process, July 1
60%
Work-in-process, July 31
40%
The journal entry to record the transferred-in cost added in July would include
A debit to work-in-process inventory (Department 1) for $200,000
A debit to work-in-process inventory (Department 2) for $200,000
A debit to work-in-process inventory (Department 2) for $220,000
No entry would be required
4 points
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
Related Documents
Recommended textbooks for you

Managerial Accounting: The Cornerstone of Busines...
Accounting
ISBN:9781337115773
Author:Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher:Cengage Learning

Cornerstones of Cost Management (Cornerstones Ser...
Accounting
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Cengage Learning

Principles of Cost Accounting
Accounting
ISBN:9781305087408
Author:Edward J. Vanderbeck, Maria R. Mitchell
Publisher:Cengage Learning

Excel Applications for Accounting Principles
Accounting
ISBN:9781111581565
Author:Gaylord N. Smith
Publisher:Cengage Learning

College Accounting, Chapters 1-27
Accounting
ISBN:9781337794756
Author:HEINTZ, James A.
Publisher:Cengage Learning,
Principles of Accounting Volume 2
Accounting
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax College
Recommended textbooks for you
- Managerial Accounting: The Cornerstone of Busines...AccountingISBN:9781337115773Author:Maryanne M. Mowen, Don R. Hansen, Dan L. HeitgerPublisher:Cengage LearningCornerstones of Cost Management (Cornerstones Ser...AccountingISBN:9781305970663Author:Don R. Hansen, Maryanne M. MowenPublisher:Cengage LearningPrinciples of Cost AccountingAccountingISBN:9781305087408Author:Edward J. Vanderbeck, Maria R. MitchellPublisher:Cengage Learning
- Excel Applications for Accounting PrinciplesAccountingISBN:9781111581565Author:Gaylord N. SmithPublisher:Cengage LearningCollege Accounting, Chapters 1-27AccountingISBN:9781337794756Author:HEINTZ, James A.Publisher:Cengage Learning,Principles of Accounting Volume 2AccountingISBN:9781947172609Author:OpenStaxPublisher:OpenStax College

Managerial Accounting: The Cornerstone of Busines...
Accounting
ISBN:9781337115773
Author:Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher:Cengage Learning

Cornerstones of Cost Management (Cornerstones Ser...
Accounting
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Cengage Learning

Principles of Cost Accounting
Accounting
ISBN:9781305087408
Author:Edward J. Vanderbeck, Maria R. Mitchell
Publisher:Cengage Learning

Excel Applications for Accounting Principles
Accounting
ISBN:9781111581565
Author:Gaylord N. Smith
Publisher:Cengage Learning

College Accounting, Chapters 1-27
Accounting
ISBN:9781337794756
Author:HEINTZ, James A.
Publisher:Cengage Learning,
Principles of Accounting Volume 2
Accounting
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax College