Exam 2

docx

School

Angelo State University *

*We aren’t endorsed by this school

Course

MISC

Subject

Accounting

Date

Feb 20, 2024

Type

docx

Pages

21

Uploaded by ProfessorArmadilloPerson1008

Report
QUESTION 1 1. THE FOLLOWING INFORMATION IS USED FOR QUESTIONS 1 – 11. Test Company uses a normal, job-order cost system to determine product cost.  The following jobs were in process on July 1.     Job 603 Job 604 Job 605 Direct materials $1,600 $1,200 $800 Direct labor 2,000 1,500 1,000 Applied overhead 1,500 1,125 750   During July, Test Company completed Jobs 603 and 604 and began production on Jobs 701 and 702.  Jobs 605, 701, and 702 were still in process on July 31.  There was on finished goods inventory on July 1.  Test Company delivered Job 603 and billed the customer for cost plus 20%.   The following costs were added to production during July.     Job 603 Job 604 Job 605 Job 701 Job 702 Direct materials $850 $1,000 $1,200 $650 $500 Direct labor 1,000 1,500 1,600 800 600 Applied overhead 750 1,125 1,200 600 450   Actual overhead cost for July totaled $4,250.  The overhead variance is considered immaterial. Determine the balance of work-in-process inventory as of July 31. Note: Give your answer using dollar signs and commas but no decimal points (cents). Example: $12,345 4 points QUESTION 2 1. THE FOLLOWING INFORMATION IS USED FOR QUESTIONS 1 – 11. Test Company uses a normal, job-order cost system to determine product cost.  The following jobs were in process on July 1.     Job 603 Job 604 Job 605 Direct materials $1,600 $1,200 $800 Direct labor 2,000 1,500 1,000 Applied overhead 1,500 1,125 750  
During July, Test Company completed Jobs 603 and 604 and began production on Jobs 701 and 702.  Jobs 605, 701, and 702 were still in process on July 31.  There was on finished goods inventory on July 1.  Test Company delivered Job 603 and billed the customer for cost plus 20%.   The following costs were added to production during July.     Job 603 Job 604 Job 605 Job 701 Job 702 Direct materials $850 $1,000 $1,200 $650 $500 Direct labor 1,000 1,500 1,600 800 600 Applied overhead 750 1,125 1,200 600 450   Actual overhead cost for July totaled $4,250.  The overhead variance is considered immaterial. Determine the cost of goods manufactured for July. Note: Give your answer using dollar signs and commas but no decimal points (cents). Example: $12,345 4 points QUESTION 3 1. THE FOLLOWING INFORMATION IS USED FOR QUESTIONS 1 – 11. Test Company uses a normal, job-order cost system to determine product cost.  The following jobs were in process on July 1.     Job 603 Job 604 Job 605 Direct materials $1,600 $1,200 $800 Direct labor 2,000 1,500 1,000 Applied overhead 1,500 1,125 750   During July, Test Company completed Jobs 603 and 604 and began production on Jobs 701 and 702.  Jobs 605, 701, and 702 were still in process on July 31.  There was on finished goods inventory on July 1.  Test Company delivered Job 603 and billed the customer for cost plus 20%.   The following costs were added to production during July.     Job 603 Job 604 Job 605 Job 701 Job 702 Direct materials $850 $1,000 $1,200 $650 $500 Direct labor 1,000 1,500 1,600 800 600 Applied overhead 750 1,125 1,200 600 450   Actual overhead cost for July totaled $4,250.  The overhead variance is considered immaterial.
Determine the balance of finished goods inventory as of July 31. Note: Give your answer using dollar signs and commas but no decimal points (cents). Example: $12,345 4 points QUESTION 4 1. THE FOLLOWING INFORMATION IS USED FOR QUESTIONS 1 – 11. Test Company uses a normal, job-order cost system to determine product cost.  The following jobs were in process on July 1.     Job 603 Job 604 Job 605 Direct materials $1,600 $1,200 $800 Direct labor 2,000 1,500 1,000 Applied overhead 1,500 1,125 750   During July, Test Company completed Jobs 603 and 604 and began production on Jobs 701 and 702.  Jobs 605, 701, and 702 were still in process on July 31.  There was on finished goods inventory on July 1.  Test Company delivered Job 603 and billed the customer for cost plus 20%.   The following costs were added to production during July.     Job 603 Job 604 Job 605 Job 701 Job 702 Direct materials $850 $1,000 $1,200 $650 $500 Direct labor 1,000 1,500 1,600 800 600 Applied overhead 750 1,125 1,200 600 450   Actual overhead cost for July totaled $4,250.  The overhead variance is considered immaterial. Determine cost of goods sold for July before adjusting for the overhead variance. Note: Give your answer using dollar signs and commas but no decimal points (cents). Example: $12,345 4 points QUESTION 5 1. THE FOLLOWING INFORMATION IS USED FOR QUESTIONS 1 – 11. Test Company uses a normal, job-order cost system to determine product cost.  The following jobs were in process on July 1.  
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
  • Access to all documents
  • Unlimited textbook solutions
  • 24/7 expert homework help
  Job 603 Job 604 Job 605 Direct materials $1,600 $1,200 $800 Direct labor 2,000 1,500 1,000 Applied overhead 1,500 1,125 750   During July, Test Company completed Jobs 603 and 604 and began production on Jobs 701 and 702.  Jobs 605, 701, and 702 were still in process on July 31.  There was on finished goods inventory on July 1.  Test Company delivered Job 603 and billed the customer for cost plus 20%.   The following costs were added to production during July.     Job 603 Job 604 Job 605 Job 701 Job 702 Direct materials $850 $1,000 $1,200 $650 $500 Direct labor 1,000 1,500 1,600 800 600 Applied overhead 750 1,125 1,200 600 450   Actual overhead cost for July totaled $4,250.  The overhead variance is considered immaterial. Determine cost of goods sold for July after adjusting for the overhead variance. Note: Give your answer using dollar signs and commas but no decimal points (cents). Example: $12,345 4 points QUESTION 6 1. THE FOLLOWING INFORMATION IS USED FOR QUESTIONS 1 – 11. Test Company uses a normal, job-order cost system to determine product cost.  The following jobs were in process on July 1.     Job 603 Job 604 Job 605 Direct materials $1,600 $1,200 $800 Direct labor 2,000 1,500 1,000 Applied overhead 1,500 1,125 750   During July, Test Company completed Jobs 603 and 604 and began production on Jobs 701 and 702.  Jobs 605, 701, and 702 were still in process on July 31.  There was on finished goods inventory on July 1.  Test Company delivered Job 603 and billed the customer for cost plus 20%.   The following costs were added to production during July.  
  Job 603 Job 604 Job 605 Job 701 Job 702 Direct materials $850 $1,000 $1,200 $650 $500 Direct labor 1,000 1,500 1,600 800 600 Applied overhead 750 1,125 1,200 600 450   Actual overhead cost for July totaled $4,250.  The overhead variance is considered immaterial. The journal entry to record the materials requisitioned for Job 603 in July would include A debit to cost of goods manufactured (Job 603) for $850 A debit to direct materials used (Job 603) for $850 A debit to work-in-process inventory (Job 603) for $850 A debit to raw materials inventory (Job 603) for $850 4 points QUESTION 7 1. THE FOLLOWING INFORMATION IS USED FOR QUESTIONS 1 – 11. Test Company uses a normal, job-order cost system to determine product cost.  The following jobs were in process on July 1.     Job 603 Job 604 Job 605 Direct materials $1,600 $1,200 $800 Direct labor 2,000 1,500 1,000 Applied overhead 1,500 1,125 750   During July, Test Company completed Jobs 603 and 604 and began production on Jobs 701 and 702.  Jobs 605, 701, and 702 were still in process on July 31.  There was on finished goods inventory on July 1.  Test Company delivered Job 603 and billed the customer for cost plus 20%.   The following costs were added to production during July.     Job 603 Job 604 Job 605 Job 701 Job 702 Direct materials $850 $1,000 $1,200 $650 $500 Direct labor 1,000 1,500 1,600 800 600 Applied overhead 750 1,125 1,200 600 450   Actual overhead cost for July totaled $4,250.  The overhead variance is considered immaterial. The journal entry to record the direct labor cost for Job 603 in July would include
A debit to work-in-process inventory (Job 603) for $1,000 A debit to wages expense (Job 603) for $1,000 A debit to cost of goods manufactured (Job 603) for $1,000 A debit to direct labor (Job 603) for $1,000 4 points QUESTION 8 1. THE FOLLOWING INFORMATION IS USED FOR QUESTIONS 1 – 11. Test Company uses a normal, job-order cost system to determine product cost.  The following jobs were in process on July 1.     Job 603 Job 604 Job 605 Direct materials $1,600 $1,200 $800 Direct labor 2,000 1,500 1,000 Applied overhead 1,500 1,125 750   During July, Test Company completed Jobs 603 and 604 and began production on Jobs 701 and 702.  Jobs 605, 701, and 702 were still in process on July 31.  There was on finished goods inventory on July 1.  Test Company delivered Job 603 and billed the customer for cost plus 20%.   The following costs were added to production during July.     Job 603 Job 604 Job 605 Job 701 Job 702 Direct materials $850 $1,000 $1,200 $650 $500 Direct labor 1,000 1,500 1,600 800 600 Applied overhead 750 1,125 1,200 600 450   Actual overhead cost for July totaled $4,250.  The overhead variance is considered immaterial. The journal entry to record the overhead applied to Job 603 in July would include A debit to cost of goods manufactured for $750 A debit to overhead control for (Job 603) for $750 A debit to various overhead cost accounts (Job 603) for $750 A debit to work-in-process inventory (Job 603) for $750 4 points QUESTION 9 1. THE FOLLOWING INFORMATION IS USED FOR QUESTIONS 1 – 11.
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
  • Access to all documents
  • Unlimited textbook solutions
  • 24/7 expert homework help
Test Company uses a normal, job-order cost system to determine product cost.  The following jobs were in process on July 1.     Job 603 Job 604 Job 605 Direct materials $1,600 $1,200 $800 Direct labor 2,000 1,500 1,000 Applied overhead 1,500 1,125 750   During July, Test Company completed Jobs 603 and 604 and began production on Jobs 701 and 702.  Jobs 605, 701, and 702 were still in process on July 31.  There was on finished goods inventory on July 1.  Test Company delivered Job 603 and billed the customer for cost plus 20%.   The following costs were added to production during July.     Job 603 Job 604 Job 605 Job 701 Job 702 Direct materials $850 $1,000 $1,200 $650 $500 Direct labor 1,000 1,500 1,600 800 600 Applied overhead 750 1,125 1,200 600 450   Actual overhead cost for July totaled $4,250.  The overhead variance is considered immaterial. The journal entry to record the completion of Job 603 would include A debit to work-in-process inventory (Job 603) for $2,600 A debit to cost of goods manufactured (Job 603) for $7,700 A debit to finished goods inventory (Job 603) for $2,600 A debit to finished goods inventory(Job 603) for $7,700 4 points QUESTION 10 1. THE FOLLOWING INFORMATION IS USED FOR QUESTIONS 1 – 11. Test Company uses a normal, job-order cost system to determine product cost.  The following jobs were in process on July 1.     Job 603 Job 604 Job 605 Direct materials $1,600 $1,200 $800 Direct labor 2,000 1,500 1,000 Applied overhead 1,500 1,125 750  
During July, Test Company completed Jobs 603 and 604 and began production on Jobs 701 and 702.  Jobs 605, 701, and 702 were still in process on July 31.  There was on finished goods inventory on July 1.  Test Company delivered Job 603 and billed the customer for cost plus 20%.   The following costs were added to production during July.     Job 603 Job 604 Job 605 Job 701 Job 702 Direct materials $850 $1,000 $1,200 $650 $500 Direct labor 1,000 1,500 1,600 800 600 Applied overhead 750 1,125 1,200 600 450   Actual overhead cost for July totaled $4,250.  The overhead variance is considered immaterial. The journal entry to record the sale of Job 603 would include A debit to sales for $7,700 A debit to finished goods inventory (Job 603) for $2,600 A debit to accounts receivable for $9,240 A debit to cost of goods sold for $3,120 4 points QUESTION 11 1. THE FOLLOWING INFORMATION IS USED FOR QUESTIONS 1 – 11. Test Company uses a normal, job-order cost system to determine product cost.  The following jobs were in process on July 1.     Job 603 Job 604 Job 605 Direct materials $1,600 $1,200 $800 Direct labor 2,000 1,500 1,000 Applied overhead 1,500 1,125 750   During July, Test Company completed Jobs 603 and 604 and began production on Jobs 701 and 702.  Jobs 605, 701, and 702 were still in process on July 31.  There was on finished goods inventory on July 1.  Test Company delivered Job 603 and billed the customer for cost plus 20%.   The following costs were added to production during July.     Job 603 Job 604 Job 605 Job 701 Job 702 Direct materials $850 $1,000 $1,200 $650 $500 Direct labor 1,000 1,500 1,600 800 600
Applied overhead 750 1,125 1,200 600 450   Actual overhead cost for July totaled $4,250.  The overhead variance is considered immaterial. The journal entry to record the actual overhead cost for July would include A credit to overhead control for $4,250 A debit to overhead variance for $125 A debit to overhead control for $4,250 A debit to work-in-process inventory for $4,250 4 points QUESTION 12 1. Test Company reported the following costs for Job 101.     Job 101 Direct materials $2,500 Direct labor 1,500 Applied overhead 1,000   Overhead is applied at a rate of $10 per direct labor hour. Quality inspection showed three units in the job to be defective.  The units were reworked using additional direct materials of $100 and additional direct labor of five hours at a cost of $75.  The rework is considered normal spoilage. Determine the total cost of Job 101. Note: Give your answer using dollar signs and commas but no decimal points (cents). Example: $12,345 4 points QUESTION 13 1. Test Company uses a normal, process costing system to determine product cost.  The company reported the following production activity in Department 2 for July.   Work-in-process inventory, July 1 1,000 units Units transferred in from Department 1 8,000 units Units completed and transferred to finished goods 6,500 units   Determine the number of units in work-in-process inventory in Department 2 as of July 31.
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
  • Access to all documents
  • Unlimited textbook solutions
  • 24/7 expert homework help
Note: Give your answer using commas.  Do not include the word “units.” Example: 12,345 4 points QUESTION 14 1. Test Company uses a normal, process costing system to determine product cost.  The company reported the following production activity in Department 2 for July.   Work-in-process inventory, July 1 1,000 units Units transferred in from Department 1 8,000 units Units completed and transferred to finished goods 6,500 units   Determine the number of units started and completed in Department 2 in July. Note: Give your answer using commas.  Do not include the word “units.” Example: 12,345 4 points QUESTION 15 1. THE FOLLOWING INFORMATION IS USED FOR QUESTIONS 15 – 25. Test Company uses a normal, process costing system to determine product cost.  The company uses the first-in, first-out (FIFO) method to account for equivalent units and costs in beginning work-in-process.  The product passes through two departments: Department 1 and Department 2.  In Department 2, all direct materials are added at the beginning of the process.  The following information is available for Department 2 in July.   Work-in-process, July 1        Units 5,000 units      Costs             Direct materials $25,000           Conversion cost 16,000           Transferred-in cost 20,000 July activity        Units             Transferred in 50,000 units           Completed and transferred out 45,000 units      Costs added  
          Direct materials $400,000           Conversion cost 184,000           Transferred-in-cost 200,000 Percentage of completion        Work-in-process, July 1 60%      Work-in-process, July 31 40%   Determine the number of units to account for from the July production report. Note: Give your answer using commas.  Do not include the word “units.” Example: 12,345 4 points QUESTION 16 1. THE FOLLOWING INFORMATION IS USED FOR QUESTIONS 15 – 25. Test Company uses a normal, process costing system to determine product cost.  The company uses the first-in, first-out (FIFO) method to account for equivalent units and costs in beginning work-in-process.  The product passes through two departments: Department 1 and Department 2.  In Department 2, all direct materials are added at the beginning of the process.  The following information is available for Department 2 in July.   Work-in-process, July 1        Units 5,000 units      Costs             Direct materials $25,000           Conversion cost 16,000           Transferred-in cost 20,000 July activity        Units             Transferred in 50,000 units           Completed and transferred out 45,000 units      Costs added             Direct materials $400,000           Conversion cost 184,000           Transferred-in-cost 200,000 Percentage of completion        Work-in-process, July 1 60%
     Work-in-process, July 31 40%   Determine the equivalent units of output with respect to direct materials for July. Note: Give your answer using commas.  Do not include the word “units.” Example: 12,345 4 points QUESTION 17 1. THE FOLLOWING INFORMATION IS USED FOR QUESTIONS 15 – 25. Test Company uses a normal, process costing system to determine product cost.  The company uses the first-in, first-out (FIFO) method to account for equivalent units and costs in beginning work-in-process.  The product passes through two departments: Department 1 and Department 2.  In Department 2, all direct materials are added at the beginning of the process.  The following information is available for Department 2 in July.   Work-in-process, July 1        Units 5,000 units      Costs             Direct materials $25,000           Conversion cost 16,000           Transferred-in cost 20,000 July activity        Units             Transferred in 50,000 units           Completed and transferred out 45,000 units      Costs added             Direct materials $400,000           Conversion cost 184,000           Transferred-in-cost 200,000 Percentage of completion        Work-in-process, July 1 60%      Work-in-process, July 31 40%   Determine the equivalent units of output with respect to conversion cost for July. Note: Give your answer using commas.  Do not include the word “units.”
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
  • Access to all documents
  • Unlimited textbook solutions
  • 24/7 expert homework help
Example: 12,345 4 points QUESTION 18 1. THE FOLLOWING INFORMATION IS USED FOR QUESTIONS 15 – 25. Test Company uses a normal, process costing system to determine product cost.  The company uses the first-in, first-out (FIFO) method to account for equivalent units and costs in beginning work-in-process.  The product passes through two departments: Department 1 and Department 2.  In Department 2, all direct materials are added at the beginning of the process.  The following information is available for Department 2 in July.   Work-in-process, July 1        Units 5,000 units      Costs             Direct materials $25,000           Conversion cost 16,000           Transferred-in cost 20,000 July activity        Units             Transferred in 50,000 units           Completed and transferred out 45,000 units      Costs added             Direct materials $400,000           Conversion cost 184,000           Transferred-in-cost 200,000 Percentage of completion        Work-in-process, July 1 60%      Work-in-process, July 31 40%   Determine the equivalent units of output with respect to transferred-in cost for July. Note: Give your answer using commas.  Do not include the word “units.” Example: 12,345 4 points
QUESTION 19 1. THE FOLLOWING INFORMATION IS USED FOR QUESTIONS 15 – 25. Test Company uses a normal, process costing system to determine product cost.  The company uses the first-in, first-out (FIFO) method to account for equivalent units and costs in beginning work-in-process.  The product passes through two departments: Department 1 and Department 2.  In Department 2, all direct materials are added at the beginning of the process.  The following information is available for Department 2 in July.   Work-in-process, July 1        Units 5,000 units      Costs             Direct materials $25,000           Conversion cost 16,000           Transferred-in cost 20,000 July activity        Units             Transferred in 50,000 units           Completed and transferred out 45,000 units      Costs added             Direct materials $400,000           Conversion cost 184,000           Transferred-in-cost 200,000 Percentage of completion        Work-in-process, July 1 60%      Work-in-process, July 31 40%   Determine the cost per equivalent unit with respect to direct materials for July. Note: Give your answer using dollar signs and carry your answer to the nearest cent. Examples: $12.34 or $12.00
4 points QUESTION 20 1. THE FOLLOWING INFORMATION IS USED FOR QUESTIONS 15 – 25. Test Company uses a normal, process costing system to determine product cost.  The company uses the first-in, first-out (FIFO) method to account for equivalent units and costs in beginning work-in-process.  The product passes through two departments: Department 1 and Department 2.  In Department 2, all direct materials are added at the beginning of the process.  The following information is available for Department 2 in July.   Work-in-process, July 1        Units 5,000 units      Costs             Direct materials $25,000           Conversion cost 16,000           Transferred-in cost 20,000 July activity        Units             Transferred in 50,000 units           Completed and transferred out 45,000 units      Costs added             Direct materials $400,000           Conversion cost 184,000           Transferred-in-cost 200,000 Percentage of completion        Work-in-process, July 1 60%      Work-in-process, July 31 40%   Determine the cost per equivalent unit with respect to conversion cost for July.
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
  • Access to all documents
  • Unlimited textbook solutions
  • 24/7 expert homework help
Note: Give your answer using dollar signs and carry your answer to the nearest cent. Examples: $12.34 or $12.00 4 points QUESTION 21 1. THE FOLLOWING INFORMATION IS USED FOR QUESTIONS 15 – 25. Test Company uses a normal, process costing system to determine product cost.  The company uses the first-in, first-out (FIFO) method to account for equivalent units and costs in beginning work-in-process.  The product passes through two departments: Department 1 and Department 2.  In Department 2, all direct materials are added at the beginning of the process.  The following information is available for Department 2 in July.   Work-in-process, July 1        Units 5,000 units      Costs             Direct materials $25,000           Conversion cost 16,000           Transferred-in cost 20,000 July activity        Units             Transferred in 50,000 units           Completed and transferred out 45,000 units      Costs added             Direct materials $400,000           Conversion cost 184,000           Transferred-in-cost 200,000 Percentage of completion        Work-in-process, July 1 60%      Work-in-process, July 31 40%   Determine the cost per equivalent unit with respect to transferred-in cost for July.
Note: Give your answer using dollar signs and carry your answer to the nearest cent. Examples: $12.34 or $12.00 4 points QUESTION 22 1. THE FOLLOWING INFORMATION IS USED FOR QUESTIONS 15 – 25. Test Company uses a normal, process costing system to determine product cost.  The company uses the first-in, first-out (FIFO) method to account for equivalent units and costs in beginning work-in-process.  The product passes through two departments: Department 1 and Department 2.  In Department 2, all direct materials are added at the beginning of the process.  The following information is available for Department 2 in July.   Work-in-process, July 1        Units 5,000 units      Costs             Direct materials $25,000           Conversion cost 16,000           Transferred-in cost 20,000 July activity        Units             Transferred in 50,000 units           Completed and transferred out 45,000 units      Costs added             Direct materials $400,000           Conversion cost 184,000           Transferred-in-cost 200,000 Percentage of completion        Work-in-process, July 1 60%      Work-in-process, July 31 40%   Determine the total cost transferred out for July. Note: Give your answer using dollars signs and commas but not decimal points (cents). Example: $12,345 4 points
QUESTION 23 1. THE FOLLOWING INFORMATION IS USED FOR QUESTIONS 15 – 25. Test Company uses a normal, process costing system to determine product cost.  The company uses the first-in, first-out (FIFO) method to account for equivalent units and costs in beginning work-in-process.  The product passes through two departments: Department 1 and Department 2.  In Department 2, all direct materials are added at the beginning of the process.  The following information is available for Department 2 in July.   Work-in-process, July 1        Units 5,000 units      Costs             Direct materials $25,000           Conversion cost 16,000           Transferred-in cost 20,000 July activity        Units             Transferred in 50,000 units           Completed and transferred out 45,000 units      Costs added             Direct materials $400,000           Conversion cost 184,000           Transferred-in-cost 200,000 Percentage of completion        Work-in-process, July 1 60%      Work-in-process, July 31 40%   Determine the total cost of work-in-process inventory as of July 31. Note: Give your answer using dollars signs and commas but not decimal points (cents). Example: $12,345 4 points QUESTION 24 1. THE FOLLOWING INFORMATION IS USED FOR QUESTIONS 15 – 25. Test Company uses a normal, process costing system to determine product cost.  The company uses the first-in, first-out (FIFO) method to account for equivalent units and costs in beginning work-in-process. 
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
  • Access to all documents
  • Unlimited textbook solutions
  • 24/7 expert homework help
The product passes through two departments: Department 1 and Department 2.  In Department 2, all direct materials are added at the beginning of the process.  The following information is available for Department 2 in July.   Work-in-process, July 1        Units 5,000 units      Costs             Direct materials $25,000           Conversion cost 16,000           Transferred-in cost 20,000 July activity        Units             Transferred in 50,000 units           Completed and transferred out 45,000 units      Costs added             Direct materials $400,000           Conversion cost 184,000           Transferred-in-cost 200,000 Percentage of completion        Work-in-process, July 1 60%      Work-in-process, July 31 40%   The journal entry to record the direct materials cost added in July would include A debit to work-in-process inventory (Department 2) for $425,000 No entry would be required A debit to work-in-process inventory (Department 2) for $400,000 A debit to raw materials inventory for $400,000 4 points
QUESTION 25 1. THE FOLLOWING INFORMATION IS USED FOR QUESTIONS 15 – 25. Test Company uses a normal, process costing system to determine product cost.  The company uses the first-in, first-out (FIFO) method to account for equivalent units and costs in beginning work-in-process.  The product passes through two departments: Department 1 and Department 2.  In Department 2, all direct materials are added at the beginning of the process.  The following information is available for Department 2 in July.   Work-in-process, July 1        Units 5,000 units      Costs             Direct materials $25,000           Conversion cost 16,000           Transferred-in cost 20,000 July activity        Units             Transferred in 50,000 units           Completed and transferred out 45,000 units      Costs added             Direct materials $400,000           Conversion cost 184,000           Transferred-in-cost 200,000 Percentage of completion        Work-in-process, July 1 60%      Work-in-process, July 31 40%   The journal entry to record the transferred-in cost added in July would include A debit to work-in-process inventory (Department 1) for $200,000
A debit to work-in-process inventory (Department 2) for $200,000 A debit to work-in-process inventory (Department 2) for $220,000 No entry would be required 4 points
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
  • Access to all documents
  • Unlimited textbook solutions
  • 24/7 expert homework help