INTER. ACCOUNTING - CONNECT+ALEKS ACCESS
10th Edition
ISBN: 9781264770335
Author: SPICELAND
Publisher: MCG
expand_more
expand_more
format_list_bulleted
Question
error_outline
This textbook solution is under construction.
Students have asked these similar questions
In 2019, PJD Construction Corporation began construction work under a 3-year contract. The contract price was P4,000,000. PJD uses the percentage-of-completion method/over time for financial accounting purposes. The income to be recognized each year is based on the proportion of costs incurred to total estimated costs for completing the contract. The financial statement presentation relating to this contract at December 31, 2019 was as follows:
What is the recognized revenue in 2019?
Calculate the amount of revenue to be recognized in 2020 and 2021.
Calculate the construction costs to be expensed in 2021.
Prepare the journal entry at December 31, 2021, to record long-term contract revenues, expenses, and losses for 2021.
What is the balance in the Contract Asset/Liability account at December 31, 2020 and 2021?
Show how the construction contract would be reported on the SFP and the income statement for the year ended December 31, 2021.
Assume that Cullumber uses the zero-profit or completed-contract method. What would be the journal entry recorded on December 31, 2021?
Jhun Co. recognizes construction revenues and expenses using the percentage of completion method. During 2019, a single long-term contract was started, which continued through the year 2020. Information the project follows:
2019
Account receivable on contract 100,000
Construction expense 105,000
Construction in progress 122,000
Partial billings on contract 100,000
2020
Account receivable on contract 300,000
Construction expense 192,000
Construction in progress 364,000
Partial billings on contract 420,000
Profit recognized in 2019 should be?
Profit recognized in 2020 should be?
Knowledge Booster
Similar questions
- Sheridan Construction Inc., which has a calendar year end, has entered into a non-cancellable fixed-price contract for $2.8 million beginning September 1, 2023, to build a road for a municipality. It has been estimated that the road construction will be complete by June 2025. The following data pertain to the construction period. 2023 Costs to date $850,000 Estimated costs to complete 1,650,000 Progress billings to date (non-refundable) 924,000 Cash collected to date 750,000 2024 $1,782,550 532,450 2,296,000 2,157,000 2025 $2,346,000 0 2,800,000 2,800,000arrow_forwardIn 2021, Crane Corporation began construction work under a three-year contract. The contract price is $ 480000. Crane uses the percentage-of-completion method for financial accounting purposes. The income to be recognized each year is based on the proportion of costs incurred to total estimated costs for completing the contract. The financial statement presentations relating to this contract at December 31, 2021, follow: Balance Sheet Accounts receivable—construction contract billings $ 192000 Construction in progress $ 600000 Less contract billings 480000 Costs and recognized profit in excess of billings 120000 Income Statement Income (before tax) on the contract recognized in 2021 $ 120000 How much cash was collected in 2021 on this contract? $ 480000 $ 48000 $ 288000 $ 192000arrow_forwardIn 2025, Sunland Construction Corp. began construction work under a 3-year contract. The contract price was $1,090,000. Sunland uses the percentage-of-completion method for financial accounting purposes. The income to be recognized each year is based on the proportion of cost incurred to total estimated costs for completing the contract. The financial statement presentations relating to this contract at December 31, 2025, are shown below. Balance Sheet Accounts receivable Construction in process Less: Billings Costs and recognized profit in excess of billings Income Statement $16,600 $62,500 58,000 4,500 Income (before tax) on the contract recognized in 2025 (a) Your answer is correct. How much cash was collected in 2025 on this contract? (b) Portion of contract billings collected $ eTextbook and Media * Your answer is incorrect. $20,000 41400 What was the initial estimated total income before tax on this contract? Income before tax on this contract $ 4500 Attempts: 2 of 15 usedarrow_forward
- Blossom Construction Company uses the percentage-of-completion method of accounting. In 2021, Blossom began work on a contract it had received which provided for a contract price of $47500000. Other details follow: 2021 Costs incurred during the year $22000000 Estimated costs to complete as of December 31 16000000 Billings during the year 21500000 Collections during the year 10500000 What should be the gross profit recognized in 2021?arrow_forwardDuring the year 2019, Height Cons began work on a contract for 3,700,000. Costs incurred during the year 1,800,000. Estimated costs to complete as of December 31= 1,200,000 Billings during the year1,650,000 Collections during the year 975,000 It uses the percentage-of-completion method. Find reporting gross profit?arrow_forwardSuppose that a contract is started on January 1, 2018, with an estimated completion date of December 31, 2019. The final contract price is P1,500,000. In the first year covering January 1 to December 31, 2018: Cost incurred amounted to P600,000. Half the work on the contract was completed. Certificates of work completed have been issued to the value of P750,000. It is estimated with reasonable certainty that further costs to completion in 2019 will be P600,000. Requirements: 1. The contract is certified at what percentage of completion? 2. At Dec 31, 2018, the entity will recognize how much profit? 3. At Dec 31, 2018, the entity will recognize how much contract asset?arrow_forward
- The Lao Construction Company recognizes revenue over time according to percentage of completion for its long-term construction contracts. In 2024, Lao began work on a construction contract. Information on this contract at the end of 2024 is as follows: Cost incurred during the year $ 1,500,000 Estimated additional cost to complete 6,000,000 Gross profit recognized in 2024 250,000 What is the contract price (total revenue) on this contract?arrow_forwardIn 2020, Blue Construction Corp. began construction work under a 3-year contract. The contract price was $1,060,000. Blue uses the percentage-of-completion method for financial accounting purposes. The income to be recognized each year is based on the proportion of cost incurred to total estimated costs for completing the contract. The financial statement presentations relating to this contract at December 31, 2020, are shown below. Balance Sheet Accounts receivable $16,600 Construction in process $63,700 Less: Billings 65,400 Costs and recognized profit in excess of billings -1,700 Income Statement Income (before tax) on the contract recognized in 2020 $19,110 (a) How much cash was collected in 2020 on this contract? Portion of contract billings collected $enter a dollar amount (b) What was the initial estimated total income before tax on this contract? Income before tax on this contract $enter a…arrow_forwardIn 2020, Steinrotter Construction Corp. began construction work under a 3-year contract. The contract price was $1,000,000. Steinrotter uses the percentage-of-completion method for financial accounting purposes. The income to be recognized each year is based on the proportion of cost incurred to total estimated costs for completing the contract. The financial statement presentations relating to this contract at December 31, 2020, are shown below. Balance Sheet Accounts receivable $18,000 Construction in process $65,000 Less: Billings 61,500 Costs and recognized profit in excess of billings 3,500 Income Statement Income (before tax) on the contract recognized in 2020 $19,500 Instructions a. How much cash was collected in 2020 on this contract? b. What was the initial estimated total income before tax on this contract?arrow_forward
- In 2020, Grouper Construction Corp. began construction work under a 3-year contract. The contract price was $1,060,000. Grouper uses the percentage-of-completion method for financial accounting purposes. The income to be recognized each year is based on the proportion of cost incurred to total estimated costs for completing the contract. The financial statement presentations relating to this contract at December 31, 2020, are shown below. Balance Sheet Accounts receivable $17,700 Construction in process $68,300 Less: Billings 61,300 Costs and recognized profit in excess of billings 7,000 Income Statement Income (before tax) on the contract recognized in 2020 $16,392 (a) How much cash was collected in 2020 on this contract? Portion of contract billings collected $enter a dollar amount (b) What was the initial estimated total income before tax on this contract? Income before tax on this contract $enter a…arrow_forwardABC Inc. began operations on July 1,2019. The company recognizes income from long term construction contracts under the percentage of completion method in its financial statements and under the cost recovery method for income tax purposes. Income under each are as follows: 2019 Cost recovery- P 0 % of completion- P 700,000 2020 Cost recovery- P 800,000 % of completion- P 1,280,000 2021 Cost recovery- P 1,350,000 % of completion- P 1,700,000 The income tax rate was 32% for 2019. Based on a new law, for years after 2019, the tax rate is 34%. There are no other temporary differences. ABC should report in its December 31,2021 a deferred tax liability ofarrow_forward3. Suppose the estimated costs to complete at the end of 2019 are $80 million instead of $60 million. Determinethe amount of revenue and gross profit or loss to be recognized in 2019 assuming Sanderson recognizes revenue over time according to percentage of completion.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Intermediate Accounting: Reporting And AnalysisAccountingISBN:9781337788281Author:James M. Wahlen, Jefferson P. Jones, Donald PagachPublisher:Cengage Learning
Intermediate Accounting: Reporting And Analysis
Accounting
ISBN:9781337788281
Author:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:Cengage Learning