7-1 Final Project: Project Management Plan Report
Tamika Robinson
QSO-345: Project Management for CAPM Certification
Jim Cotton
December 10, 2023
2
INTRODUCTION
A project is a temporary endeavor to create a unique product, service, or result (PMI, 2021). It has a
beginning and an end and includes tasks that must be completed within a specific timeframe to accomplish
a goal. Projects are widely performed in many industries today as they help ensure continuous
improvement and are a way to ensure organizations can focus on what matters.
Projects consist of the following phases: initiation, planning, execution, monitoring and controlling, and
closing (PMI, 2021). While these phases are vital to ensuring a successful project outcome, managing the
efforts is just as important. Project managers lead these efforts to ensure all tasks within each phase are
completed accordingly. They are responsible for planning, organizing, and managing projects from start to
finish (PMI, 2021). Project managers are vital to managing the project team, communicating with
stakeholders, and ensuring projects are completed on time and within budget and scope.
SUMMARY OF CASE STUDY
Romet Limited designs and manufactures rotary natural gas meters and electrical instruments for
worldwide customers (Mark, 2019). As they grow, they need a new plant to handle daily operations
efficiently and meet growing customer demand. As the project manager responsible for procuring the new
facility, I’ll be responsible for project planning activities. The following project management plan report will
outline all deliverables to ensure the project’s completion, including the project charter, stakeholder
management plan, communication matrix, scope management plan, quality management plan, schedule
management plan, and cost management plan.
PROJECT MANAGEMENT PLAN
1.
Project Charter
Project Name:
Project Destiny
Project Manager:
Tamika Robinson
Latest Revision Date:
November 18, 2023
Overview
Project Destiny involves relocating Romet Limited's operations from one of its existing facilities to another. This
project charter will outline the vital information necessary to facilitate this move. Romet has a functional
project structure; its hierarchy is organized around traditional functioning departments (PMI, 2021). Project
team members will be assigned from different functional areas within the organization.
CEO Brent Colliver has requested that Project Destiny be completed within schedule and budget. The
deliverables are concise and straightforward, and many tasks must be done sequentially, so the appropriate
project methodology is predictive (waterfall). With predictive project methodology, a project follows a linear
progression through the five project stages of initiation, planning, execution, monitoring, and closure (PMI,
2021).
Project Description
To aid continuous company growth, Romet Limited will be moving to a new plant to give them an additional
20,00 square feet and expanded material flow. Fourteen sequential activities are required to complete this
3
relocation. The lease will need to be finalized, and the appropriate permits and zoning approvals must be
obtained before moving to the new plant operations in subsequent order. The move must be completed by
December 21, and operations must be continued during this relocation.
Project Purpose
An initiation kick-off meeting occurred to inform all key stakeholders about the reason for Project Destiny. The
project aims to move to a large facility, providing additional space and improving material flow. Romet's
company aimed to machine critical components for rotary natural gas meters and electric instruments in-
house. As the company continues to grow and acquire additional equipment, there is a need for a larger facility
to continue to meet Romet's strategic goals. From a planning perspective, we will complete all the
documentation necessary to determine what will be needed to complete this project in time.
Project Objectives
Operations must continue while the plant is being moved, and measurable project objectives are outlined
below.
Finalizing lease
Obtain permits
Acquire zoning approvals
Electrical and pneumatic construction
Quality/supervision pod construction
Anodizing line installation
Machine shop equipment removal and reinstallation
Construct climate control proving room
Assembly and paint line relocation
Auxiliary equipment
Office construction
Installation of information technology services
Office move
Success criteria are that each of these objectives is completed according to the requirements within the
allotted time provided while ensuring no disruption to existing ongoing operations.
Business Case
Project Destiny will benefit Romet as the new facility will provide 20,000 additional square feet and improve
the layout. Additional square footage means additional equipment, resulting in financial growth for the
company. At this time, it is unknown if any other alternatives were provided. Based on the organizational
structure, the determination to take this approach was made by Brent Collver, CEO of Romet, when it was
determined that there was a need for a larger facility.
Requirements
The high-level essential requirement in Project Destiny is to ensure that Romet operations are moved timely to
the Timberlea Boulevard location.
Assumptions
Each project deliverable will be completed within its estimated timeframe.
Acts of God or weather will not impact the move.
The project will be completed within the allotted budget.
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
4
Constraints
The project must be completed by December 21.
The project must be completed within the allotted budget.
Dependencies
The lease for the new plant needs to be finalized.
Permits and zoning approvals must be done before moving to the new facility.
To ensure operations continue, each area needs to ensure enough work/part availability before
shutting down for relocation.
A proving room and an office for the quality department and its supervisors must be put up before
equipment/materials are moved to the new plant.
Electrical and pneumatic construction needs to be completed before equipment installation.
Sign off for inventory and proper equipment installation before beginning operations in the new plant
and closing the project.
Risks
Inability to continue operations while moving the plant.
Lease, permits, and zoning approvals were not provided on time.
Budget increases.
Inadequate testing/technical support.
Resource availability.
Observance of holidays such as Thanksgiving and Christmas may result in delays.
Project Deliverables
The execution of deliverables will ensure that at the close of Project Destiny, Romet will be completely
operational at the new larger facility. The milestones that will be provided in the following section outline what
needs to be completed to achieve our project objectives. To ensure each deliverable is proceeding according to
plan, monitoring the progress of each deliverable is vital to ensure we remain on track.
Project Milestones
Milestone
ID
Milestone Name
Projected Milestone
Dates
Dependency
Milestone Description
1
Finalize lease
5/1 – 5/26
---
Lawyers to finalize lease details at the
new location.
2
Obtain permits
5/29 – 7/7
1
Obtain permits for building.
3
Zoning approval
5/29 – 7/21
1
Zoning approvals are acquired for
new buildings.
4
Electrical and
pneumatic
construction
7/24 – 9/29
2,3
All components related to electrical
and pneumatic construction are
being handled.
5
Quality/supervis
or pod
construction
7/24 – 9/29
2,3
Construction within the building for
pods for quality supervisors.
6
Anodizing line
installation
7/24 – 9/15
2,3
Full installation of the anodizing line.
7
Machine shop
equipment
9/18 – 9/29
4,6
Machine shop equipment will be
disassembled and reassembled at the
5
Milestone
ID
Milestone Name
Projected Milestone
Dates
Dependency
Milestone Description
removal and
reinstallation
new location.
8
Climate
controlled
proving room
construction
10/2 – 10/27
5
The new climate-controlled proving
room is built.
9
Assembly
relocation
10/2 – 10/6
7
Assembly operations are relocated to
the new location.
10
Paint line
relocation
10/9 – 11/17
9
Paint line operations are relocated to
the new location.
11
Auxiliary
equipment
11/20 – 11/24
10
All auxiliary equipment will be
established at the new location.
12
Office
construction
10/2 – 12/15
5
The contractor is building a new
office at the new location.
13
Information
technology
services
10/2 – 12/15
5
IT services are established and fully
functional at the new facility
14
Office move
12/16 – 12/21
12,13
Offices are moved to a new location.
15
Project end
--
8,11,14
The project is closed when all
milestones above have been
completed.
Table 1, Project Milestones
Project Manager
The project manager is Tamika Robinson, who ensures project goals are met. The project manager must
monitor progress, evaluate performance, and ensure stakeholder satisfaction (PMI, 2021). Based on the
organizational structure at Romet Limited, Tamika is allowed to make small decisions to maintain Project
Destiny’s progress. Still, she has no authority to make decisions regarding the budget. She will need to seek
final decisions and direction with her manager.
Project Roles and Responsibilities
Name
Role
Responsibilities
Brent Colliver
Project Sponsor
Actively promotes the project, approves deliverables,
and is responsible for providing the funding.
Kent Masters
Director of
Operations
Oversee and ensure plant operations during the
planned relocation.
Tamika Robinson
Project Manager
Responsible for ensuring the project team works
efficiently and diligently to complete deliverables
within time and budget. Tamika manages the project,
will update stakeholders, and ensure the project
remains on track.
William Smith
Lawyer
Expected to finalize the details of the lease timely.
Jerry McIntyre
Contractor
Contractor responsible for plant construction and
equipment installation. He must provide resources and
ensure the electrical and pneumatic construction is
completed before installing equipment.
Kay Tuttle
Dept. Head of
Responsible for overseeing the machining area and
6
Name
Role
Responsibilities
Machining
ensuring enough parts are built before the shutdown
for relocation. She’ll need the plant facility and
equipment to meet all requirements after the project.
Jared White
Dept. Head of
Anodizing
Responsible for overseeing the anodizing area and
needs to ensure this area of the manufacturing process
meets all requirements after the project.
Sam Rose
Dept. Head of
Assembly
Responsible for overseeing the assembling of the
manufacturing process and will ensure enough work
before the shutdown for the relocation. She’ll need to
ensure this area meets all requirements after the
project.
Gary Jones
Dept. Head of
Proving
Responsible for coordinating with Measurement
Canada to aid with certifying the testing of equipment
after it has been relocated and installed in the new
building.
Tami Doe
Product Manager
Equipment specialist who will be responsible for being
part of the coordination and testing of equipment after
it has been relocated to the new building.
Mark Hartwell
Technology
Manager (project
team)
Responsible for ensuring all technical work is handled
on time. He will help ensure vendor tasks align with
requirements and within time and budget. He must
validate and provide a sign-off on all designs before
completion.
Any May
Regulatory and
Permits Specialist
(project team)
Responsible for licensing and permitting work. She
must review permit and license applications to ensure
they follow policies, codes, and statutes. Any will
collaborate with the company lawyer to ensure the
permits, licenses, and zoning approvals are obtained
timely.
Julie Sebastian
HR Assistant
(project team)
Responsible for ensuring human resource leadership
continues to be provided to operational leaders and
employees during this relocation.
David Clark
Machine Shop
Supervisor (project
team)
Responsible for overseeing operational work in the
Machining area before and after the shutdown for the
relocation.
Mike Litten
Inventory Control
and Movement
(project team)
Responsible for taking inventory of all equipment and
parts before the relocation begins and after they have
been moved to the new building.
James Terry
Vendor/Contractor
Coordinator
(project team)
Responsible for working with Jerry to coordinate
additional plant construction and equipment
installation resources.
Table 2, Project Roles and Responsibilities
Project Budget
CEO and Project Sponsor Brent Colliver has established a budget based on the estimated schedule. It won't be
easy to have additional project costs approved.
Project Exit Criteria
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
7
All 14 actions must be completed on time and within budget to close Project Destiny. This represents the
closure phase of the project. Customer acceptance criteria will be met when it is confirmed that all inventoried
equipment is accounted for, adequately reassembled, and operating accordingly.
Sponsor and Project Approvers Acceptance
Based on the organizational structure and the predictive method used for Project Destiny, the project sponsor
ultimately determines the success of the process and signs off on it.
Approver
Role or Title
Acceptance Date
Brent Colliver
Sponsor
April 27
Table 3, Approval of Sponsors
2.
Stakeholder Management Plan
Stakeholder Analysis Results
Stakeholder
Name
Title
Needs/Expectations
Influenc
e
Interest
Power
Brent Colliver
CEO
Brent needs the project deliverables completed within
the allotted budget and preferably ahead of schedule.
High
5
5
Paul Brown
CFO
Paul will oversee the finances allotted for this project,
which will aid with the company’s strategic goal. Needs
to ensure this project is handled within the allotted
budget.
High
5
4
Kent Masters
Director of
Operations
Kent needs to ensure that plant operations during the
planned relocations.
High
5
4
William
Smith
Lawyer
William is expected to finalize the details of the lease
timely.
Medium
3
2
George Dyer
Architect
George will conduct research and develop architectural
plans and designs. He is expected to provide his
knowledge of architectural design, building materials
and systems zoning, and building codes.
Medium
3
3
Jerry
McIntyre
Contractor
Jerry is the contractor responsible for plant construction
and equipment installation. He must provide resources
and ensure the electrical and pneumatic construction is
completed before installing equipment.
Low
4
3
Kay Tuttle
Dept. Head
of Machining
Kay will oversee the machining area and ensure enough
parts are built before the shutdown for relocation. She’ll
need the plant facility and equipment to meet all
requirements after the project.
Medium
2
2
Jared White
Dept. Head
of Anodizing
Jared will oversee the anodizing area and needs to
ensure this area of the manufacturing process meets all
requirements after the project.
Medium
2
2
Sam Rose
Dept. Head
of Assembly
Sam will oversee the assembling of the manufacturing
process and will ensure enough work before the
shutdown for the relocation. She’ll need to ensure this
area meets all requirements after the project.
Medium
4
4
8
Stakeholder
Name
Title
Needs/Expectations
Influenc
e
Interest
Power
Tamika
Robinson
Project
Manager
Tamika needs the project team to work efficiently and
diligently to complete deliverables within time and
budget. Tamika manages the project, will update
stakeholders, and ensure the project remains on track.
High
5
4
Gary Jones
Dept. Head
of Proving
Gary will need to coordinate with Measurement Canada
to aid with certifying the testing of equipment after it
has been relocated and installed in the new building.
Medium
3
5
Mary
Johnson
HR Director
Mary will need to ensure human resource leadership
continues to be provided to operational leaders and
employees during this relocation.
Low
1
2
Tami Doe
Product
Manager
Tami is the equipment specialist who will need to be
part of the coordination and testing of equipment after
it has been relocated to the new building.
High
4
2
Mark
Hartwell
Technology
Manager
Mark will work directly with the project team to ensure
all technical work is handled on time. He will help with
ensuring vendor tasks are in line with requirements and
within time and budget. He must validate and provide a
sign-off on all designs before completion.
High
4
5
Any May
Regulatory
and Permits
Specialist
Any is part of the project team responsible for licensing
and permitting work. She must review permit and
license applications to ensure they follow policies,
codes, and statutes. Any will collaborate with the
company lawyer to ensure the permits, licenses, and
zoning approvals are obtained timely.
Medium
2
2
Julie
Sebastian
HR Assistant
Julie is part of the project team that will ensure human
resource leadership continues to be provided to
operational leaders and employees during this
relocation.
Low
2
2
David Clark
Machine
Shop
Supervisor
David is part of the project team that will continue to
oversee operational work being performed in the
Machining area before and after the shutdown for the
relocation.
Medium
2
2
Mike Litten
Inventory
Control and
Movement
Mike will need to ensure that inventory of all equipment
and parts is taken before the relocation begins and after
they have been moved to the new building.
Medium
2
2
James Terry
Vendor/Cont
ractor
Coordinator
James is part of the project team and will need to work
with Jerry to coordinate additional resources for plant
construction and equipment installation.
Medium
2
2
Table 1, Stakeholder Analysis Results
Stakeholder Register
Stakeholder
Name
Title
Contact
Engagemen
t Level
Attitude
Communication Requirements
Project
Impact
Brent
Colliver
CEO
905-519-3208
Ext.001
b.colliver@romet
High
Champion
Weekly project status
meetings
Email for any impediments
10
9
Stakeholder
Name
Title
Contact
Engagemen
t Level
Attitude
Communication Requirements
Project
Impact
.com
or roadblocks with the
schedule and budget.
Paul Brown
CFO
905-519-3208
Ext.002
p.brown@romet.
com
Medium-
High
Supporter
Monthly project status
meetings.
Ad-hoc meetings to discuss
impediments that will
impact planned budget.
9
Kent
Masters
Director of
Operations
905-519-3208
Ext.003
k.masters@rome
t.com
High
Supporter
Weekly project status
meetings
9
William
Smith
Lawyer
905-519-3208
Ext.004
w.smith@romet.
com
Medium-
Low
Neutral
Weekly project status
meetings
Email, IM, and phone call
5
George Dyer
Architect
905-519-3208
Ext.005
g.dyer@romet.c
om
Medium
Supporter
Weekly project status
meetings
Email, IM, and phone call
6
Jerry
McIntyre
Contractor
905-519-3208
Ext.006
j.mcintyre@rom
et.com
Medium
Supporter
Weekly project status
meetings
Email, IM, and phone call
7
Tamika
Robinson
Project
Manager
905-519-3208
Ext.007
t.roibnson@rom
et.com
High
Champion
Weekly project status
meetings
Available and respond to all
emails, IMs, and phone calls
regarding the project.
4
Kay Tuttle
Dept. Head
of
Machining
905-519-3208
Ext.008
k.tuttle@romet.c
om
Low
Neutral
Monthly project status
meetings.
4
Jared White
Dept. Head
of
Anodizing
905-519-3208
Ext.009
j.white@romet.c
om
Medium-
Low
Critic
Weekly project status
meetings.
Rarely responds to emails,
so contact via phone for
project questions.
8
Sam Rose
Dept. Head
of
Assembly
905-519-3208
Ext.010
s.rose@romet.co
m
Medium-
Low
Supporter
Weekly project status
meetings.
CC on all project related
communications.
9
Gary Jones
Dept. Head
of Proving
905-519-3208
Ext.011
g.jones@romet.c
om
Medium-
Low
Neutral
IM prior to email or phone
calls.
CC on all meeting minutes
from weekly project status
meetings.
8
Mary
HR
905-519-3208
Low
Supporter
Weekly project status
3
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
10
Stakeholder
Name
Title
Contact
Engagemen
t Level
Attitude
Communication Requirements
Project
Impact
Johnson
Director
Ext.012
m.johnson@rom
et.com
meetings.
Ensure up to date project
documentation is shared,
prior to asking questions.
Tami Doe
Product
Manager
905-519-3208
Ext.013
t.jones@romet.c
om
High
Champion
Weekly project status
meetings.
Included in all stakeholder
meetings.
Responds fastest to emails
but will also take IMs or
phone calls.
6
Mark
Hartwell
Technical
Manager
905-519-3208
Ext.014
m.hartwell@rom
et.com
Medium -
High
Supporter
Weekly project status
meetings.
Ad-hoc meetings to talk
through project and any
project needs from him.
9
Any May
Regulatory
and
Permits
905-519-3208
Ext.015
a.may@romet.co
m
Medium -
Low
Supporter
Weekly project status
update meetings.
Recurring project strategy
team meetings.
Daily Stand Ups
Utilize IM, email, phone,
meeting platforms to
collaborate amongst the
project team.
4
Julie
Sebastian
HR
Assistant
905-519-3208
Ext.016
j.sebastian@rom
et.com
Low
Supporter
Weekly project status
update meetings.
Recurring project strategy
team meetings.
Daily Stand Ups
Utilize IM, email, phone,
meeting platforms to
collaborate amongst the
project team.
4
David Clark
Supervisor
905-519-3208
Ext.017
d.clark@romet.c
om
Medium
Supporter
Weekly project status
update meetings.
Recurring project strategy
team meetings.
Daily Stand Ups
Utilize IM, email, phone,
meeting platforms to
collaborate amongst the
project team.
4
Mike Litten
Inventory
Specialist
905-519-3208
Ext.018
m.litten@romet.
com
Medium-
High
Supporter
Weekly project status
update meetings.
Recurring project strategy
team meetings.
4
11
Stakeholder
Name
Title
Contact
Engagemen
t Level
Attitude
Communication Requirements
Project
Impact
Daily Stand Ups
Utilize IM, email, phone,
meeting platforms to
collaborate amongst the
project team.
James Terry
Vendor/Co
ntractor
Coordinato
r
905-519-3208
Ext.019
j.terry@romet.co
m
Medium
Supporter
Weekly project status
update meetings.
Recurring project strategy
team meetings.
Daily Stand Ups
Utilize IM, email, phone,
meeting platforms to
collaborate amongst the
project team.
4
Table 2, Stakeholder Registry
3.
Communications Matrix
Communicating in projects is critical to a project’s success, and due to the fixed schedule and budget with
Project Destiny, we need to ensure all stakeholders involved are communicated effectively and timely. A
communication matrix is a vital project tool to outline the communication management plan for a project
(PMI, 2021). Projects will benefit from a communication matrix as it helps set stakeholders’ expectations on
how and when they will receive project updates.
Communication
Method
Objective of
Communication
Medium
Frequency
Stakeholder
Audience
Owner
Deliverable
Format
Kickoff meeting
Introduce the
team to the
project and
explain the
charter.
Virtual
(Zoom)
or Face-
to-face
Once
Project
team,
internal
stakeholder
s, external
stakeholder
s
Project
manager
Presentation
deck and
meeting
notes.
Presentation
deck provided in
soft copy for all
participants.
Weekly project
check-in
meetings
Discuss what
has been
accomplished,
upcoming tasks
and anticipated
roadblocks or
challenges.
Virtual or
Face-to-
face
Weekly
Project
team,
internal
stakeholder
s, external
stakeholder
s
Project
manager
Presentation
deck and
meeting
notes.
Presentation
deck provided in
soft copy for all
participants
along with
captured
meeting
minutes.
Technology
Meetings
Planning
sessions to
review
requirement,
execution
sessions to
Virtual or
Face-to-
face
Weekly
and as
needed
Project
team,
Technical
team and
partners
Project
manager
/Technic
al
manager
Presentation
deck and
meeting
notes.
Presentation
deck provided in
soft copy for all
participants
along with
meeting
12
Communication
Method
Objective of
Communication
Medium
Frequency
Stakeholder
Audience
Owner
Deliverable
Format
discuss
technical
development
solutions or
impediments,
testing.
minutes.
Stakeholder/Ste
ering
Committee
meetings
Informative
meetings with
executive
leadership or
steering
committee on
project status.
Virtual or
Face-to-
face or
Conferen
ce call
After
milestone
completion
Executive
leadership
responsible
for project
and
providing
support and
steering
committee.
Project
manager
Project
schedule and
meeting
notes.
Schedule
provided in soft
copy for all
participants
along with
meeting
minutes.
Daily Stand Ups
Quick meeting
to discuss what
was completed
the day before,
what will be
completed
today and any
impediments.
Virtual or
Face-to-
face
Daily
Project
Team
Project
Manager
Huddled
discussion.
Meeting notes
captured shared
with
participants.
Retrospective
meeting
(Lessons
Learned)
Occurs at the
end/completion
of project to
reflect on what
was successful
and what could
be improved.
Virtual or
Face-to-
face
Once
Project
team,
internal
stakeholder
s, external
stakeholder
s
Project
Manager
/Product
Owner
Presenting
anonymous
feedback
gathered
before
meeting, and
‘white board’
details
captured
Share
information
captured with
all participants.
Table 3, Communication Matrix
4.
Scope Management Plan
Scope Statement
To aid continuous company growth, Romet Limited will be moving to a new plant to give them an additional
20,00 square feet and expanded material flow. A scope management plan was developed to provide insight
into the scope of Project Destiny. A scope management plan is a required collection of processes to ensure all
the relevant tasks are completed (PMI, 2021). It provides a structure for explaining the project scope by
breaking it down into smaller manageable pieces to validate with stakeholders.
Fourteen sequential activities are required to complete this relocation. The lease will need to be finalized, and
the appropriate permits and zoning approvals must be obtained before moving to the new plant operations in
subsequent order. The move must be completed by December 21, and operations must be continued during
this relocation. In addition to defining the scope and providing deliverable breakdowns, the scope
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
13
management plan will also outline validations requiring sign-off and monitoring controls to ensure the scope is
managed appropriately.
Work Breakdown Structure (WBS) Hierarchy
Figure 1, Hierarchal Work Breakdown Structure as Described by PMI®
WBS Dictionary
WBS Coding
Element Name
Description
1.1
Legal and Regulatory
1.1.1
Lease
Lawyers to finalize lease
1.1.2
Permits
Obtain permits
1.1.3
Zoning
Acquire zoning approvals
1.1.4
Build
Select contractor for the initial build
1.1.5
Certification
Measurement Canada to complete certification of
equipment after relocated
1.2
Initial build-out
1.2.1
Quality department
Build office pod for quality department
1.2.2
Supervisors
Build office pod for super
1.2.3
Proving room
Build proving room
1.3
Plant
1.3.1
Plant construction
Construction of the plant
1.3.2
Proving room
Construction on proving room
1.3.3
Electrical
Electrical system
1.3.4
Pneumatic
Pneumatic system
1. Project
Destiny
1.1 Legal and
Regulatory
1.1.1 Lease
1.1.2 Permits
1.1.3 Zoning
1.1.4 Build
1.1.5
Certification
1.2 Initial Build-
Out
1.2.1 Quality
Dept.
1.2.2 Supervisors
1.2.3 Proving
room
1.3 Plant
1.3.1 Plant
construction
1.3.2 Proving
room
1.3.3 Electrical
1.3.4 Pneumatic
1.4 Equipment
1.4.1 Anodizing
1.4.2 Removal
1.4.3 Move
1.4.4 Install
1.5 Moving
1.5.1 Machine
shop
1.5.2 Assembly
1.5.3 Paint line
1.5.4 Auxiliary
1.5.5 IT
1.5.6 Office
1.6 Transition
1.6.1 Machined
parts
1.6.2 Assembled
parts
1.6.3 Customer
deliveries
1.7 Close
1.7.1 Project end
14
WBS Coding
Element Name
Description
1.4
Equipment
1.4.1
Anodizing
Installation of the the anodizing line
1.4.2
Removal
Removal of machine shop equipment
1.4.3
Move
Move the machine shop equipment to the new
facility
1.4.4
Install
Install the machine shop equipment
1.5
Moving
1.5.1
Machine shop
Move the machine shop to the new facility
1.5.2
Assembly
Move the assembly line to the new facility
1.5.3
Paint line
Move the paint line to the new facility
1.5.4
Auxiliary
Move auxiliary equipment to the new facility
1.5.5
IT
Transfer information technology services
1.5.6
Office
Office move
1.6
Transition
1.6.1
Machined parts
Create inventory of machined parts
1.6.2
Assembled parts
Create inventory of assembled parts
1.6.3
Customer deliveries
Support customer deliveries
1.7
Close
1.7.1
Project End
Project closure
Table 1, WBS Dictionary
The work breakdown structure (WBS) is a way to break down project deliverables into more manageable
smaller groups that can easily be managed, tracked, and accounted for (PMI, 2021). The above WBS dictionary
outlines Project Destiney milestones and deliverables from start to finish. This tool can aid project managers in
tracking the progress of deliverables and help identify potential scope risks.
Scope Verification
Having a clear understanding of the requirements and what is to be delivered is vital during the scope
verification process. Key team members and stakeholders must review the deliverables to ensure they meet
the given acceptance criteria. Change requests for the project should be documented and evaluated to ensure
they don’t impact on the project. Tools like variance analysis will also help ensure the project stays on track
(PMI, 2021). Any variations from the projected plan must be assessed, and remedial actions must be taken.
Lastly, a closure report is necessary during the closing phase to ensure all the work is completed and delivered
as agreed (PMI, 2021).
Scope Control
The project is broken down into different milestones. Each deliverable tied to each milestone must be
reviewed for accuracy and completeness. Any unforeseen changes or challenges during the project will require
review with the project sponsor, Brent Culliver. Brent has clarified that we must stay within budget and
complete this project by December 21. So, an evaluation will be required to determine a change's impact on
the timeline and budget. He will assess each change request and provide an approval or denial. This strategy
will ensure stakeholders are aware of any project impacts, ensuring the project remains on track.
5.
Quality Management Plan
Introduction
15
The quality management plan for Project Destiny will outline the quality standards, assurance, and control
limitations necessary to ensure the proper quality for this effort is being met. Ensuring that project deliverables
are met will require focusing on testing, inspecting, and identifying any issues. The project manager must
establish a procedure for assessing readiness to deliver the project’s objective. The plan’s success will be
assessed considering the completion of every task against the planned timeline and budget.
Quality Management Approach
Quality Standard Name
Quality Standard Type
Quality Metric
Quality Standard
Timeline Evaluation
Process Quality
Frequent project
timeline
monitoring
Ensure project remains
within timeframe
Equipment Procurement
Product & Process
Quality
Equipment meets
standard
specifications
Equipment meets
functional stands for
processing and product
output
Inventory Valuation
Product Quality
Manufactured
inventory must
continue to me
standards
Inventory meets quality
standards and meets
98% customer
satisfaction rate
Business Continuation
Product Quality
Disassemble
equipment and
reassemble
equipment at new
location, while
continuing to ship
products
Continue to provide
products to customers
while relocating to the
new facility
Table 1, Quality Approach Standards and Requirements
Quality Assurance
Quality Standard
Name
QA Process Name
QA Methodology
Frequency
Timeline Evaluation
Timeline Audit
As each milestone is
completed, the project
manager will review the
timeline.
Any variances can
allow for appropriate
modifications
During and after
milestone completion
Equipment
Procurement
Equipment Review
Team to perform equipment
checks to validate equipment
performance weekly for one
month. Then standard monthly
quality evaluations.
Weekly/Monthly
Inventory Valuation
Inventory
Quality team to perform
Weekly
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
16
Quality Standard
Name
QA Process Name
QA Methodology
Frequency
Assessment
weekly audits to ensure
inventory quality
Business
Continuation
Business
Continuation
Analysis
Project Team/Dept. Heads to
track monthly product being
shipped to customers during
the facility relocation
Monthly
Table 2, Quality Assurance Processes, Methodology, and Frequency
Quality Control
Quality Standard Name
Quality Thresholds
Quality Response
Timeline Evaluation
Evaluate projected to actual to
stay as close within timeline
Regular review of timeline to
modify as necessary. Milestones
that are completed sooner, can
compensate for those that take
longer
Equipment Procurement
100% functionality performance
resulting in no product defects
Evaluation of new equipment to
address any maintenance
concerns/deficiencies to fix or
address with vendor within an
appropriate timeframe before
impacting product quality
Inventory Valuation
Inventory defects rate of <10%
for a product produced
Complete end-to-end
evaluation of production
inventory to determine the
cause of defects
Business Continuation
Ensure the number of pre-
produced products continues to
be produced within the same
timeline established for the
facility relocation
Any impacts to the project
timeline will require
amendments for additional pre-
processed materials to ensure
production until project closure
Table 3, Quality Thresholds and Responses
6.
Schedule Management Plan
The schedule management plan outlines how the project will be planned, designed, executed, monitored, and
controlled (PMI, 2021). It will outline the project manager and team's approach, methodologies, milestones,
and timeline for each activity. This document will be used to measure Project Destiny's performance. We'll
define variance thresholds to take corrective action when necessary to ensure we can complete the project on
time and within budget.
To prevent a project from deviating too far from the planned schedule, earned value metrics can provide
insight into a project's current performance and predict future behavior (PMI, 2021). Regarding the schedule,
the schedule variance (SV) measures whether a project is behind or ahead of schedule (PMI, 2021). This will
17
aid the project manager in monitoring the project's schedule to ensure no additional finances are incurred.
The schedule performance index (SPI) monitors how efficiently the project progresses compared to the plan
(PMI, 2021). It helps evaluate the accuracy of a schedule and how well the project team is using its time. The
schedule management plan will outline regular intervals to manage the schedule and establish baselines and
action plans when variances occur.
Schedule Management Approach
First, we'll need to identify all the activities and tasks to be completed for the project. This can be done with
working sessions, consulting with team members/SMEs, or assessing previous projects. Then, determine the
order of each activity and task. Creating a network diagram can aid in visually indicating the sequential order.
Some activities may need to be done sequentially, and some could be done in parallel. Then, we'll need to
estimate how long each will take. Analogous and three-point estimating techniques were used for Project
Destiny to estimate activity durations. Then, we'll need to develop a schedule by inputting all activities
sequentially by their durations. Using this schedule will help with developing a timeline. Lastly, we'll need to
review with vital stakeholders. Necessary adjustments will be made before finalizing the schedule.
Activity list
The activity list outlines all the activities required for Project Destiny. The chart will include the activity
name/description predecessor and the estimated work item. The project manager will be responsible for
ensuring all items are captured and continuously reviewing the WBS and timeline to ensure all items are being
handled timely.
WBS
WBS Name
Predecessor WBS ID
Estimated Time (Weeks)
1.1
Legal and Regulatory
1.1.1
Lease Finalization
-
4
1.1.2
Obtain Permits
1.1.1
10
1.1.3
Zoning Approvals
1.1.1
8
1.1.4
Select Contractor
-
-
1.1.5
Certification Completion
-
-
1.2
Initial build-out
1.2.1
Office construction
1.2.2, 1.2.3
12
1.2.2
Construct pod for quality department
1.1.2, 1.1.3
16
1.2.3
Construct pod for supervisors
1.1.2, 1.1.3
1.3
Plant
1.3.1
Plant construction
-
-
1.3.2
Build/Construct proving room
1.2.2
4
1.3.3
Construct electrical system
1.1.2, 1.1.3
16
1.3.4
Construct pneumatic system
1.1.2, 1.1.3
1.4
Equipment
1.4.1
Anodizing line installation
1.1.2, 1.1.3
14
1.4.2
Remove machines from current
location
1.3.3, 1.4.1
2
1.4.3
Install machines at new location
1.3.3, 1.4.1
2
1.5
Moving
1.5.1
Machine relocation
-
-
1.5.2
Assembly relocation
1.4.2, 1.4.3
1
1.5.3
Paint line relocation
1.5.2
6
1.5.4
Auxiliary equipment relocation
1.5.3
1
18
WBS
WBS Name
Predecessor WBS ID
Estimated Time (Weeks)
1.5.5
Information technology services
1.2.2, 1.2.3
12
1.5.6
Office move
1.2.1, 1.5.5
1
1.6
Transition
1.6.1
Create inventory of machined parts
-
-
1.6.2
Create inventory of assembled parts
-
-
1.6.3
Support customer deliveries
-
-
1.7
Close
1.7.1
Project End
1.3.2, 1.5.4, 1.5.6
-
Table 1, Project Activity List
Network diagram
The network diagram visually maps the schedule and activity work sequence (PMI, 2021). It can be referred
back to aid with tracking progress for each stage.
Project Sequencing and Critical Path
The table below will cover the project's sequence. The table will include the activity sequence, its
corresponding estimated time, and a critical path indicator. Delays can impact Project Destiny, so this will help
plan each activity's duration from start to completion. The project manager will ensure the timeline is not
negatively impacted.
Activity Path Sequence
Total Duration
Critical Path Y/N
1.1, 1.1.1, 1.1.2, 1.1.3, 1.1.4,
1.1.5
22 weeks
Yes
1.2, 1.2.1, 1.2.2, 1.2.3
28 weeks
Yes
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
19
Activity Path Sequence
Total Duration
Critical Path Y/N
1.3, 1.3.1, 1.3.2, 1.3.3, 1.3.4
20 weeks
No
1.4, 1.4.1, 1.4.2, 1.4.3
18 weeks
No
1.5, 1.5.1, 1.5.2, 1.5.3, 1.5.4,
1.5.5, 1.5.6
21 weeks
Yes
Table 2, Project Activity Sequencing and Durations
7.
Cost Management Plan
Monitoring project costs is necessary; a cost management plan is vital when dealing with project expenses. A
cost management plan includes all activities to estimate, monitor, and control all costs for a project (PMI,
2021). This plan will include all cost management methodologies to ensure Project Destiny can be completed
within the allotted budget. The plan will outline the project's cost breakdown, reporting formats, cost
monitoring techniques, and control techniques to include corrective and change management actions to
ensure the project remains on track to complete deliverables.
To prevent a project from deviating too far from the planned budget, earned value metrics can provide insight
into a project's current performance and predict future behavior (PMI, 2021). About cost, the cost variance
(CV) can tell us the difference between the budgeted amount versus the actual project costs (PMI, 2021). This
measurement can tell us if the project is doing financially well. Another metric used to measure the project
cost is the cost performance index (CPI). It measures a project's financial performance and planned resources'
cost-effectiveness (PMI, 2021). In Project Destiny, it will represent the amount of work completed for every
action performed. This is an excellent indicator of a project's health. This cost management plan will provide all
costs associated with Project Destiny, cost baselines established, and action plans when variances occur.
Cost Management Approach
This plan is critical as it is a comprehensive outline of Project Destiny’s budget and will be used throughout this
project. This document is used to house all project costs, both direct and indirect costs (PMI, 2021). Based on
the 14 tasks that need to be accomplished, the accounting department used analogous and three-point cost
estimations. Although there were no indications of a previous move, the analogous estimating was selected by
comparing it to a similar previous project. It was combined with the three-point estimating, which factors the
best case, most likely case, and the worst case to make an estimation (PMI, 2021). When the project begins,
the manager must monitor this plan to ensure we don’t exceed the budget. The project manager will establish
routine project budget reviews. Not only will these reviews ensure issues are dealt with early to give the
project team sufficient time to address them before they become more expensive, but they will also ensure
the actual costs are in line with the budget. Cost variances are the difference between the budgeted and actual
project costs (PMI, 2021). When a recurring review of the cost management plan has been established, we’ll
need to establish a control plan to ensure proper change management and corrective actions are in place. The
project manager will consistently monitor the project to take proactive corrective actions when costs go off
track and need to be adjusted. Communication with the project sponsor and key stakeholders will be
necessary when unexpected project costs are incurred to obtain authorization for changed requirements or
necessary expenses to the budget. The overall goal is to ensure this project remains within the assigned
budget.
20
Project Costs
The following table is an estimation of the cost for all the work that is associated with Project Destiny scope.
The analogous and three-point cost estimation techniques were leveraged. Using the previously developed
work breakdown, an estimated cost has been assigned to each activity.
WBS ID
WBS Name
Estimated Cost
1.1
Legal and Regulatory
1.1.1
Lease Finalization
$5,000
1.1.2
Obtain Permits
$3,000
1.1.3
Zoning Approvals
$10,000
1.1.4
Select Contractor
-
1.1.5
Certification Completion
-
1.2
Initial build-out
1.2.1
Office construction
$188,000
1.2.2
Construct pod for quality department
$50,000
1.2.3
Construct pod for supervisors
$50,000
1.3
Plant
1.3.1
Plant construction
-
1.3.2
Build/Construct proving room
$30,000
1.3.3
Construct electrical system
$30,000
1.3.4
Construct pneumatic system
$30,000
1.4
Equipment
1.4.1
Anodizing line installation
$32,000
1.4.2
Remove machines from current location
$54,000
1.4.3
Install machines at new location
$54,000
1.5
Moving
1.5.1
Machine relocation
$54,000
1.5.2
Assembly relocation
$35,000
1.5.3
Paint line relocation
$35,000
1.5.4
Auxiliary equipment relocation
$19,000
1.5.5
Information technology services
$76,000
1.5.6
Office move
$115,000
1.6
Transition
1.6.1
Create inventory of machined parts
-
1.6.2
Create inventory of assembled parts
-
1.6.3
Support customer deliveries
-
1.7
Close
1.7.1
Project closure
-
Table 1, Project Cost Breakdown
Reporting Format
The project manager will monitor project costs throughout the project. A cost report will be provided to the
project sponsor and all other relevant stakeholders. The report will be sent out via email and indicated during
the weekly project status meeting that it was sent via email for those stakeholders who do not immediately
read their emails. The report will cover actual costs incurred compared to the original budgeted amount,
identify variances, and forecast costs based on current project spending trends. Due to the length of Project
21
Destiny, this report will be provided weekly. This report provides transparency by informing stakeholders to
help them make informed decisions about the project.
Cost Variance Response Process
CEO and project sponsor Brent Collver is adamant that this project will be completed within schedule and
without increasing the budget. $870,000 has been allocated for all 14 activities and $30,000 for reserve. Even
though we have a small reserve, the given cost threshold will be within 0-3% because we must stay within
budget. Any negative variances will require review with the project sponsor and vital stakeholders to
determine if alternative actions are necessary quickly.
Cost Change Control
Cost change control involves constantly monitoring and tracking all allocated costs to ensure a project remains
on track. The project manager must ensure they understand the scope, all requirements, and associated
estimated cost baselines. They will then need to ensure they track the budget with the projected costs. If we
identify any overspending, the project manager will quickly schedule a review with the sponsor. We will discuss
the necessary steps to reduce costs, and if a change needs to be made, we will follow the formal process. We’ll
document the change in the log, assess its impact, obtain approval from the applicable stakeholders, revise the
baseline, update necessary documentation, and communicate the change with the project team and all other
stakeholders.
Project Budget
The following table is a breakdown of the project budget by category. The budget categories were developed
by combining similar project steps from the work breakdown structure and will also include the contingency
and management reserve values. This table provides a high level of costs for Project Destiny.
Budget Category
Cost Estimate
Contingency
Reserve
Management
Reserve
Total Budget
Legal/Regulatory
$18,000
-
-
$18,000
Construction (Labor and
Materials)
$378,000
-
-
$378,000
Equipment Relocation &
Installation
$283,000
-
-
$283,000
Information Technology
Services
$76,000
-
-
$76,000
Office Moves
$115,000
-
-
$115,000
Contingency Reserve
-
$20,000
-
$20,000
Management Reserve
-
-
$10,000
$10,000
Total Budget
$900,000
Table 2, Project Budget Breakdown
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
22
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
23
REFERENCES
Mark, K. (2019).
Project Destiny
. Ivey Business School Foundation.
Project Management Institute. (2021).
A Guide to the project management body of knowledge (PMBOK® guide)
(7th ed.)