Scenario - Identify and produce estimated building and construction costs in the workplace
This scenario covers Task 2.8 Calculate Quantities and Task 2.9 – Produce Cost Estimates
This assessment is a real-work project where you have responsibilities for producing estimated costs
for labour, materials, overheads and on-costs on various residential and commercial construction
projects within their scope of work as a trade contractor or builder.
For Tasks 2.8 and 2.9, refer to
Project Portfolio for project no. 20361 – Retail Complex
Download
Project Portfolio for project no. 20361 – Retail Complex
to determine the quantities of labour,
materials, plant and equipment for the building, and develop estimates for the construction of the
building.
The developer who is developing the project 20361 Retail Complex has asked you for a price for part
of the project.
They want a price for the ground floor Cafe and the first floor residential unit
only
for the project.
Grid at Grid B-C, 18-20.
The inclusions and exclusions are detailed below.
Inclusions:
Structural block including to both levels of the structure and including along Grid 18
Wall framing for the ground floor of the café
Rear Entry door to the unit on the ground floor
Floor system between the ground floor and first floor
Stairs to the ground to first floor
Internal and external walls on the first floor.
Windows and doors on the first floor
Roof framing system on the first floor
Roof Covering system on the first floor
External finishes to the first floor
Internal Lining
Internal Fix
Internal Finishes
Electrical
Cabinetry
Waterproofing to the terrace
Tiling to the terrace
Handrails
Exclusions:
Shop fitting to front elevation of the ground floor Café
Fit out to the ground floor café
Plumbing
The ground slab for the shop and Café.
North and south walls to shop 4 adjacent to the café.
The Quote List for Project no. 20361 contains a number of supplier prices that have been attained for
the project. These prices should be used in providing the estimate for the work.
You may refer to BAA Constructions Rates Schedules, or you may choose to research current prices
for the various items.
The estimated time to complete the work quoted is 14 weeks from commencement to hand-over.
You can use the BAA Project Estimating Template (Excel Workbook) to collate the information and
calculate the price or you can use any other electronic estimating system you would prefer to use.
The project will be allocated to a Supervisor who is a wage earning employee of the company. The
supervisor has a company car and does not get a travel allowance.
The supervisor works 48 hours per week and will have their time equally divided between four (4)
projects including this project.
The project will also use a labourer who is also a wage earner but gets paid a travelling allowance as
they are not provided a vehicle.
You can use the hourly rate template to determine this rate. These overhead costs will need to be
calculated and included the price.
Use the completed BAA Estimating Worksheets from assessment 2.8 and add in all the costing as
mentioned in the inclusions (from the scenario) and add all the additional information from key
requirements below to complete this task.
You are required to answer all questions on the
M1 Activity 2.9 - Answer sheet V1.0
Download M1
Activity 2.9 - Answer sheet V1.0
provided to you. Ensure you complete all required information
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help