ops work 2

pdf

School

Liberty University *

*We aren’t endorsed by this school

Course

361

Subject

Industrial Engineering

Date

Dec 6, 2023

Type

pdf

Pages

2

Uploaded by BrigadierWillpower11048

Report
1. Consider the following project with activities A through I. Activity Immediate Predecessor Duration (weeks) A 6 B 1 C B 1 D C 6 E C 3 F E 1 G E 4 H A,F 3 I D,H,G 2 a. Using the activity-on-arc method, draw the precedence diagram of the process. b. Using the critical path method learned in class, determine the earliest start, earliest finish, latest start and latest finish time of each activity. Finally, list the slack of each activity. After labeling the precedence diagram and performing the critical path method, we obtain the following: The slack is given in the chart below: Activity Slack A 0 B 0 C 0 D 1 E 0 F 0 G 0 H 0 I 0 c. What are the critical activities and the critical path(s) of the project? The critical activities for the project are A, B, C, E, F, G, H and I. The critical paths for the project are then: A-H-I, B-C-E-G-I, and B-C-E-F-H-I c. If activity A will take 6 weeks instead of 3 weeks to complete, what is the new project completion time? Since the activity A has a slack of 3, the project completion time will not change. d. Suppose now that we are given the following crashing information. For each week that we are able to reduce the project completion time, we are paid an extra $1000. Using the method learned in class, crash the project for as many weeks as it is profitable to do so. Clearly show which activities you will crash for each week, the cost of crashing for each week, and all of the critical paths at the end of each week. We begin week 1 of crashing with the 3 critical paths: A-H-I, B-C-E-G-I, and B-C-E-F-H-I B, C, and F can not be crashed. Therefore The only crashable activities are activity A&E which costs $300 and is less than the $1000 per week extra payment. We therefore crash Activity A&E by 1 week and bring the project completion time down to 10 weeks. We obtain the following after running the critical path method. Activity Immediate Predecessor Normal Duration (weeks) Crash Duration (weeks) Normal Cost Crash Cost Crash cost per week A 6 2 $400 $600 $200 B 1 - $200 - - C B 1 - $100 - - D C 6 4 $400 $1200 $400 E C 3 1 $600 $800 $100 F E 1 - $300 - - G E 4 3 $800 $850 $50 H A,F 3 2 $100 $500 $400 I D,H,G 2 1 $1400 $2700 $1300
We are now in week 2 of crashing and the critical paths are: A-H-I, B-C-E-G-I, B-C-D-I, B-C-E-F-H-I Activity B,C,F cannot be crashed, so the crashable options are: We could crash activity I, which costs $1300 We could crash activity A,D,E, which costs $700 We could crash activity A,D,G,H, which costs $1050 We could crash activity D,E,H, which costs $900 We could crash activity D,G,H, which costs $850 We therefore crash activity A&E&D by 1 week and bring the project completion time down to 9 weeks. We could obtain the following after running critical path method: We are now in week 3 of crashing and the critical paths are: A-H-I, B-C-E-G-I, B-C-D-I, B-C-E-F-H-I Activity B,C,E,F cannot be crashed, so the crashable options are:
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
  • Access to all documents
  • Unlimited textbook solutions
  • 24/7 expert homework help