Assignment 4
docx
keyboard_arrow_up
School
Concordia University *
*We aren’t endorsed by this school
Course
440
Subject
Finance
Date
Jan 9, 2024
Type
docx
Pages
6
Uploaded by oalmeneim
Question 1: (20 Marks)
List at least 10 types of environmental impacts over the life cycle of the product shown
in the figure below. Chart these as in Lecture 9A Slide#37, representing your judgment
of the relative impact of each life cycle state.
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
Question 2: (30 Marks)
Table 1 breaks down the number of major jobs or activities involved the development
and design of a 3-module machine.
TABLE 1
Task
Description
Direct
Predecessor
Duration
A
Plan project and get approval
2 weeks
B
Hire and assign team
A
4 weeks
C
Preliminary design
B
10 weeks
D
Detail design of Module 1
C
6 weeks
E
Detail design of Module 2
C
5 weeks
F
Electrical Layout of Module 2
E
5 weeks
G
Electrical Layout of Module 1
D
7 weeks
H
Integrate Module 1 and 2
E, G
9 weeks
I
Detail Design of Module 3
C
7 weeks
J
Integrate Module 2 and 3
F
9 weeks
K
Get Electrical H/W for Module 2 and 3
J
4 weeks
L
Make Mechanical H/W for Module 2 and 3
J
5 weeks
M
Buy H/W for module 1
H
2 weeks
N
Install H/W Module 2 and 3
K,L
6 weeks
·
Draw a PERT diagram of the above project plan and determine the expected
project duration.
Now, based on the PERT diagram, let's calculate the expected project duration.
Critical Path: A → B → C → I → J → K → N
Expected Project Duration:
TE (project) = TE (A) + TE (B) + TE (C) + TE (I) + TE (J) + TE (K) + TE (N) = 42 weeks
.
Question 3
(50 Marks
)
a)
You work in a company that develop specialized flashlights to be used in the
mining industry. In preparation for meeting with upper management you prepare
a business case that you share with your team. The following are your
assumptions:
·
The total cost of development is $600,000 over one year and it starts
Y1Q1
·
Ramp up cost is $90,000 for 9 month and it starts at Y1Q4
·
The marketing and support cost is $50,000 for one year and it starts at
Y2Q1
·
You assumed that the company could sell 5,000 units/year for 5 years
starting in Y2Q2
·
The manufacturing cost is $40, and the wholesale price is $120
·
The yearly discount rate is 10%
Is this a good project to propose to the upper management?
For the profitability of the project, we need NPV and IRR based on the assumptions given.
As the project will generate sales for 5 years starting from Y2Q1, we should estimate the cash
flow for up to Y6 to calculate if the project is profitable or not.
NPV= Cashflow
1
/(1+r)
1
+ Cashflow
2
/(1+r)
2
+ Cashflow
n
/(1+r)
n
– initial investment
From the data the cash flows for each year:
Year 1: -600,000 (development cost) - 90,000 (ramp-up cost)
Year 2: -50,000 (marketing cost) + (5,000 x $120) - (5,000 x $40) =350,000 $
Year 3-6: (5,000 x $120) - (5,000 x $40) = $ 400,000 per year
Year 1: -$624,272.72 (PV of - 690,000$)
Year 2: $289,256.19 (PV of $350,000)
Year 3,4,5,6: $1,047,889.4 (PV of $400,000 per year for 4 years)
by summing the present values of all cash flows:
NPV = 712,872.87$
Since the NPV is Positive, the project is profitable. With an IRR of 43.606%
b)
During a meeting, the management is not confident that the company can sell the
product at $120. You are tasked to estimate the minimum price that will render
this
project
not
profitable.
What
is
that
value?
For a project to not generate any profit:
total cost is equal to the total revenue, so:
690,000+ 50,000+ 5000x40x5= Yx5000x5
Thus, the minimum sales value that will make the project not profitable is
==> y=69.6$
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
Related Documents
Related Questions
Simplifying the ABC System: Approximately Relevant ABC Systems
Patterson Company produces wafers for integrated circuits. Data for the most recent year are provided:
Activity
Inserting and sorting process activities:
Expected Consumption
Ratios
Driver
Wafer A
Wafer B
1
Developing test
programs
$ 50,000
Engineering hours
0.25
0.75
Making probe
2.
60,000
Development hours
0.10
0.90
cards
Testing products
600,000
Test hours
0.60
0.40
Setting up
4.
135,000
Number of batches
0.55
0.45
batches
Engineering
Number of change
5.
90,000
0.15
0.85
design
orders
Handling wafer
6.
300,000
Number of moves
0.45
0.55
lots
7.
Inserting dies
700,000
Number of dies
0.70
0.30
Procurement process activities:
Purchasing
Number of
8.
400,000
0.20
0.80
materials
purchase orders
Unloading
9.
60,000
materials
Number of
receiving orders
0.35
0.65
Inspecting
10.
75,000
Inspection hours
0.65
0.35
materials
11.
Moving materials
500,000
Distance moved
0.50
0.50
12.
Paying suppliers
30,000
Number of invoices
0.30
0.70…
arrow_forward
I need help and an explanation to under the second part of the equation
arrow_forward
The assembly-line activities are given as follows for the manufacturing of a product:
Performance
Time (mins)
Performance
Time (mins)
6
4
5
3
Task
A
B
с
D
Predecessors
A
B
B
Task
E
F
G
H
524 2
Predecessors
C
с
D, E, F
G
For a given 7-minute cycle time after allowances, the theoretical minimum number of workstations =
(round your response to the immediate higher whole number).
arrow_forward
eBook
Show Me How
Question Content Area
High-Low Method, Cost Formulas
The controller of the South Charleston plant of Ravinia, Inc., monitored activities associated with materials handling costs. The high and low levels of resource usage occurred in September and March for three different resources associated with materials handling. The number of moves is the driver. The total costs of the three resources and the activity output, as measured by moves for the two different levels, are presented as follows:
Resource
Number of Moves
Total Cost
Forklift depreciation:
Low
4,500
$3,400
High
15,500
3,400
Indirect labor:
Low
4,500
$59,800
High
15,500
130,200
Fuel and oil for forklift:
Low
4,500
$3,285
High
15,500
11,315
Required:…
arrow_forward
please answer within the format by providing formula the detailed workingPlease provide answer in text (Without image)Please provide answer in text (Without image)Please provide answer in text (Without image)
arrow_forward
Ac
arrow_forward
Need help with this question solution general accounting
arrow_forward
Compute Lead Time
Williams Optical Inc. is considering a new lean product cell.
The present manufacturing approach produces a product in
four separate steps. The production batch sizes are 45
units. The process time for each step is as follows:
Process Step 1
Process Step 2
Process Step 3
Process Step 4
5 minutes
8 minutes
4 minutes
The time required to move each batch between steps is 5
minutes. In addition, the time to move raw materials to
Process Step 1 is also 5 minutes, and the time to move
completed units from Process Step 4 to finished goods
inventory is 5 minutes.
Value-added time
3 minutes
The new lean layout will allow the company to reduce the
batch sizes from 45 units to 3 units. The time required to
move each batch between steps and the inventory locations
will be reduced to 2 minutes. The processing time in each
step will stay the same.
Non-value-added time
Determine the value-added, non-value-added, and total
lead times, and the value-added ratio under the present
and…
arrow_forward
Reconcile the number of physical units to find the missing amounts. Determine the number of units started and completed each month.
Beginning Work in Process
Ending Work in Process
Conversion
Conversion
Complete
Complete
(percent)
(percent)
Month
February
June
September
December
Units
2,000
4,700
3,800
48
66
27
39
Units
Started
23,900
26,400
22,900
Units
Completed
23
36
59
76
Units Started
and
Completed
arrow_forward
Question Content Area
Given the following information, determine the activity rate for setups.
Activity
Total Activity-Base Usage
Budgeted Activity Cost
Setups
10,100
$63,200
Inspections
24,100
$137,300
Assembly (dlh)
72,000
$400,600
arrow_forward
THIS IS A PRACTICE SHEET, NOT GRADED!
EXCEL STYLE. ANSWER WHERE IT SAYS FORMULA
M3
arrow_forward
topic : Process Costing
PLS HELP ME ANSWER THE REQUIRED ANSWERS!
arrow_forward
Solve the questions answer of number 3 & 4
arrow_forward
QUESTION 5
The following data are for Assembly department process and once completed, will be transferred to Finishing
department.
Physical
Direct materials
Conversion costs
units
Ending work in process (31 May)
Input units
Beginning work in process (1 May)
Total costs added during May
40
200
50
$1000
$2000
$8000
0006%$
The % of completion for beginning work in process is 50% for direct materials and 60% for conversion costs.
The % of completion for ending work in process is 80% for direct materials and 30% for conversion costs.
REQUIRED:
Prepare a production cost report sheet using FIFO method to assign costs to units completed and transferred out and to
units of ending work in process. Prepare the Journal entry to record transfer to next process.
arrow_forward
Compute Lead Time
Isaacson Dental Inc. is considering a new lean product cell. The present manufacturing approach produces a product in four separate steps. The production batch sizes
are 50 units. The process time for each step is as follows:
6 minutes
12 minutes
9 minutes
3 minutes
Process Step 1
Process Step 2
Process Step 3
Process Step 4
The time required to move each batch between steps is 6 minutes. In addition, the time to move raw materials to Process Step 1 is also 6 minutes, and the time to move
completed units from Process Step 4 to finished goods inventory is 6 minutes.
The new lean layout will allow the company to reduce the batch sizes from 50 units to 2 units. The time required to move each batch between steps and the inventory
locations will be reduced to 1 minute. The processing time in each step will stay the same.
Determine the value-added, non-value-added, and total lead times, and the value-added ratio under the (a) present and (b) proposed production approaches.…
arrow_forward
gagenown/ilm/takeAssignment/takeAssignmentMain.do?invoker=&ta... A Q
eBook
Activity
Fabrication
Assembly
Setup
Inspecting
Production scheduling
Purchasing
Activity Rate
$24 per machine hour
$13 per direct labor hour
$50 per setup
$28 per inspection
$14 per production order
$11 per purchase order
The activity-base usage quantities and units produced for each product were as follows:
Elliptical Machines
Treadmill
1,687
419
53
Activity Base
Machine hours
Direct labor hours
Setups
Elliptical Machines
Treadmill
4
Product Costs using Activity Rates
Hercules Inc. manufactures elliptical exercise machines and treadmills. The products are produced in its Fabrication and Assembly production departments. In addition to production activities, several
other activities are required to produce the two products. These activities and their associated activity rates are as follows:
C
101
Print Item
%
15
5
732
$
Inspections
Production orders
Purchase orders
198
Units produced
286
Use the activity rate…
arrow_forward
Calculate Lead Time
Williams Optical Inc. is considering a new lean product cell. The present manufacturing approach produces a product in four separate steps. The production batch sizes are 64 units. The process time for each step is as follows:
Process Step 1
Process Step 2
Process Step 3
Process Step 4
7 minutes
5 minutes
4 minutes
9 minutes.
The time required to move each batch between steps is 12 minutes. In addition, the time to move raw materials to Process Step 1 is also 12 minutes, and the time to move completed units from Process Step 4 to finished goods inventory is 12
minutes.
The new lean layout will allow the company to reduce the batch sizes from 64 units to 4 units. The time required to move each batch between steps and the inventory locations will be reduced to 2 minutes. The processing time in each step will stay
the same.
Value-added time
Non-value-added time
Total lead time
Value-added ratio (as a percent)
Determine the value-added, non-value-added, and total lead…
arrow_forward
SEE MORE QUESTIONS
Recommended textbooks for you

Cornerstones of Cost Management (Cornerstones Ser...
Accounting
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Cengage Learning

Managerial Accounting: The Cornerstone of Busines...
Accounting
ISBN:9781337115773
Author:Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher:Cengage Learning
Related Questions
- Simplifying the ABC System: Approximately Relevant ABC Systems Patterson Company produces wafers for integrated circuits. Data for the most recent year are provided: Activity Inserting and sorting process activities: Expected Consumption Ratios Driver Wafer A Wafer B 1 Developing test programs $ 50,000 Engineering hours 0.25 0.75 Making probe 2. 60,000 Development hours 0.10 0.90 cards Testing products 600,000 Test hours 0.60 0.40 Setting up 4. 135,000 Number of batches 0.55 0.45 batches Engineering Number of change 5. 90,000 0.15 0.85 design orders Handling wafer 6. 300,000 Number of moves 0.45 0.55 lots 7. Inserting dies 700,000 Number of dies 0.70 0.30 Procurement process activities: Purchasing Number of 8. 400,000 0.20 0.80 materials purchase orders Unloading 9. 60,000 materials Number of receiving orders 0.35 0.65 Inspecting 10. 75,000 Inspection hours 0.65 0.35 materials 11. Moving materials 500,000 Distance moved 0.50 0.50 12. Paying suppliers 30,000 Number of invoices 0.30 0.70…arrow_forwardI need help and an explanation to under the second part of the equationarrow_forwardThe assembly-line activities are given as follows for the manufacturing of a product: Performance Time (mins) Performance Time (mins) 6 4 5 3 Task A B с D Predecessors A B B Task E F G H 524 2 Predecessors C с D, E, F G For a given 7-minute cycle time after allowances, the theoretical minimum number of workstations = (round your response to the immediate higher whole number).arrow_forward
- eBook Show Me How Question Content Area High-Low Method, Cost Formulas The controller of the South Charleston plant of Ravinia, Inc., monitored activities associated with materials handling costs. The high and low levels of resource usage occurred in September and March for three different resources associated with materials handling. The number of moves is the driver. The total costs of the three resources and the activity output, as measured by moves for the two different levels, are presented as follows: Resource Number of Moves Total Cost Forklift depreciation: Low 4,500 $3,400 High 15,500 3,400 Indirect labor: Low 4,500 $59,800 High 15,500 130,200 Fuel and oil for forklift: Low 4,500 $3,285 High 15,500 11,315 Required:…arrow_forwardplease answer within the format by providing formula the detailed workingPlease provide answer in text (Without image)Please provide answer in text (Without image)Please provide answer in text (Without image)arrow_forwardAcarrow_forward
- Need help with this question solution general accountingarrow_forwardCompute Lead Time Williams Optical Inc. is considering a new lean product cell. The present manufacturing approach produces a product in four separate steps. The production batch sizes are 45 units. The process time for each step is as follows: Process Step 1 Process Step 2 Process Step 3 Process Step 4 5 minutes 8 minutes 4 minutes The time required to move each batch between steps is 5 minutes. In addition, the time to move raw materials to Process Step 1 is also 5 minutes, and the time to move completed units from Process Step 4 to finished goods inventory is 5 minutes. Value-added time 3 minutes The new lean layout will allow the company to reduce the batch sizes from 45 units to 3 units. The time required to move each batch between steps and the inventory locations will be reduced to 2 minutes. The processing time in each step will stay the same. Non-value-added time Determine the value-added, non-value-added, and total lead times, and the value-added ratio under the present and…arrow_forwardReconcile the number of physical units to find the missing amounts. Determine the number of units started and completed each month. Beginning Work in Process Ending Work in Process Conversion Conversion Complete Complete (percent) (percent) Month February June September December Units 2,000 4,700 3,800 48 66 27 39 Units Started 23,900 26,400 22,900 Units Completed 23 36 59 76 Units Started and Completedarrow_forward
- Question Content Area Given the following information, determine the activity rate for setups. Activity Total Activity-Base Usage Budgeted Activity Cost Setups 10,100 $63,200 Inspections 24,100 $137,300 Assembly (dlh) 72,000 $400,600arrow_forwardTHIS IS A PRACTICE SHEET, NOT GRADED! EXCEL STYLE. ANSWER WHERE IT SAYS FORMULA M3arrow_forwardtopic : Process Costing PLS HELP ME ANSWER THE REQUIRED ANSWERS!arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Cornerstones of Cost Management (Cornerstones Ser...AccountingISBN:9781305970663Author:Don R. Hansen, Maryanne M. MowenPublisher:Cengage LearningManagerial Accounting: The Cornerstone of Busines...AccountingISBN:9781337115773Author:Maryanne M. Mowen, Don R. Hansen, Dan L. HeitgerPublisher:Cengage Learning

Cornerstones of Cost Management (Cornerstones Ser...
Accounting
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Cengage Learning

Managerial Accounting: The Cornerstone of Busines...
Accounting
ISBN:9781337115773
Author:Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher:Cengage Learning